grepcent public filings, reorganized for comparison

EDISON INTERNATIONAL (EIX) FY 2023 MD&A

Verbatim Item 7 Management's Discussion and Analysis from EDISON INTERNATIONAL's 10-K for fiscal year 2023. Filing date: 2024-02-22. Report date: 2023-12-31. Accession: 0000827052-24-000013.

This page reproduces the company's own Item 7 MD&A text from the linked SEC filing. It is filer text, not grepcent analysis, scoring, or investment advice.

Extracted from a later financial-section MD&A body after the formal Item 7 span was a short reference. Confidence: high.

Company profile: EIX · All MD&A years: index · Previous year: FY 2022 · Next year: FY 2024

MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

The discussion related to the results of operations and changes in financial condition for 2022 compared to 2021 is incorporated by reference to Part II, Item 7. Management's Discussion and Analysis of Financial Condition and Results of Operations in Edison International's and SCE's combined Annual Report on Form 10-K for the year ended December 31, 2022, which was filed with the SEC in February 2023.

MANAGEMENT OVERVIEW

Highlights of Operating Results

Edison International is the ultimate parent holding company of SCE and Edison Energy. SCE is an investor-owned public utility primarily engaged in the business of supplying and delivering electricity to an approximately 50,000 square mile area of southern California. Edison Energy is a global energy advisory firm providing integrated sustainability and energy solutions to commercial, industrial and institutional customers. Edison Energy's business activities are currently not material to report as a separate business segment.

Edison International's earnings are prepared in accordance with GAAP. Management uses core earnings (loss) internally for financial planning and for analysis of performance. Core earnings (loss) are also used when communicating with investors and analysts regarding Edison International's earnings results to facilitate comparisons of the company's performance from period to period. Core earnings (loss) are a non-GAAP financial measure and may not be comparable to those of other companies. Core earnings (loss) are defined as earnings attributable to Edison International shareholders less non-core items. Non-core items include income or loss from discontinued operations and income or loss from significant discrete items that management does not consider representative of ongoing earnings, such as write downs, asset impairments and other income and expense related to changes in law, outcomes in tax, regulatory or legal proceedings, and exit activities, including sale of certain assets and other activities that are no longer continuing.

Beginning July 1, 2023, SCE implemented a customer-funded wildfire self-insurance program. With the commencement of this program, Edison International and SCE no longer consider claims-related losses for wildfires to be representative of ongoing earnings and are treating such costs as non-core items prospectively. For additional information on the customer-funded self-insurance program, see "—Customer-Funded Self-Insurance."

4

Table of Contents

2023 vs. 2022
(in millions)20232022Change2021
Net income (loss) attributable to Edison International
SCE$1,474$847$627$829
Edison International Parent and Other(277)(235)(42)(70)
Edison International1,197612585759
Less: Non-core items
SCE
2017/2018 Wildfire/Mudslide Events claims and expenses, net of recoveries(634)(1,248)614(1,234)
Wildfire Insurance Fund expense(213)(214)1(215)
Other wildfire claims and expenses, net of recoveries1(34)(34)
2021 NDCTP probable disallowance(30)(30)
Customer cancellations of certain ECS data services(17)(17)
Employment litigation matter, net of recoveries10(23)33
Upstream lighting program decision(81)81
Impairments(64)64(79)
Organizational realignment charge(14)14
Sale of San Onofre nuclear fuel10(10)10
Income tax benefit2257452(195)404
Edison International Parent and Other
Customer revenues for EIS insurance contract, net of claims4236624
Income tax benefit from Settlement of 2007 – 2012 California tax audits115
Income tax expense2(9)(7)(2)(7)
Total non-core items(628)(1,153)525(982)
Core earnings (loss)
SCE2,1352,0291061,943
Edison International Parent and Other(310)(264)(46)(202)
Edison International$1,825$1,765$60$1,741
Column 1Column 2
1Charges of $4 million, $6 million and $7 million related to claims from wildfires ignited prior to July 1, 2023 are included in core earnings in 2023, 2022 and 2021, respectively. Core earnings in periods before the third quarter of 2023 have not been recast to exclude these charges.
Column 1Column 2
2SCE and Edison International Parent and Other non-core items are tax-effected at an estimated statutory rate of approximately 28%; customer revenues for EIS insurance contract are tax-effected at an estimated statutory rate of approximately 20%.

Edison International's 2023 earnings increased $585 million, driven by an increase in SCE's earnings of $627 million, offset by an increase in Edison International Parent and Other loss of $42 million. SCE's higher net income consisted of $106 million of higher core earnings and $521 million of lower non-core loss. Edison International Parent and Other higher loss consisted of $46 million of higher core loss, offset by $4 million of higher non-core earnings.

The increase in SCE's core earnings was primarily due to higher revenue due to the escalation mechanism as set forth in the 2021 GRC final decision and higher interest income on balancing account undercollections, partially offset by higher interest expense.

The increase in Edison International Parent and Other's core loss was primarily due to higher interest expense, partially offset by gains on preferred stock repurchases.

Consolidated non-core items for 2023 and 2022 for Edison International included:

Column 1Column 2
Charges of $634 million ($457 million after-tax) recorded in 2023 and $1.2 billion ($899 million after-tax) recorded in 2022 for 2017/2018 Wildfire/Mudslide Events claims and related legal expenses, net of expected recoveries from

5

Table of Contents

Column 1Column 2
FERC customers. See "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies" for further information.
Column 1Column 2
Charges of $213 million ($153 million after-tax) recorded in 2023 and $214 million ($154 million after-tax) recorded in 2022 from the amortization of SCE's contributions to the Wildfire Insurance Fund. See "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies" for further information.
Column 1Column 2
Charges of $34 million ($25 million after-tax) recorded in 2023 for wildfire claims and related legal expenses, net of expected recoveries from FERC customers, related to the Post-2018 Wildfires. See "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies" for further information.
Column 1Column 2
A charge of $30 million ($21 million after-tax) recorded in 2023 for a probable disallowance related to the reasonableness review of recorded San Onofre Units 2 and 3 decommissioning costs in the 2021 NDCTP. See "Liquidity and Capital Resources—SCE—Decommissioning of San Onofre" for more information.
Column 1Column 2
A charge of $17 million ($12 million after-tax) recorded in 2023 related to customer cancellations of certain ECS data services. See "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies" for further information.
Column 1Column 2
Insurance recovery of $10 million ($7 million after-tax) recorded in 2023 and a charge of $23 million ($16 million after-tax), net of estimated insurance recoveries, recorded in 2022. Both are related to settlement of an employment litigation matter. SCE and Edison International settled the matter following an atypical jury award.
Column 1Column 2
A charge of $81 million ($64 million after-tax) recorded in 2022 related to the Presiding Officer's Decision ("POD") in September 2022 related to SCE's Upstream Lighting Program.
Column 1Column 2
Impairment charges of $64 million ($46 million after-tax) recorded in 2022 including $47 million ($34 million after-tax) related to SCE's CSRP settlement agreement and $17 million ($12 million after-tax) related to historical capital expenditures disallowed in Track 3.
Column 1Column 2
A charge of $14 million ($10 million after-tax) recorded in 2022 related to organizational realignment services.
Column 1Column 2
Gain of $10 million ($7 million after-tax) recorded in 2022 for SCE's sale of San Onofre nuclear fuel.
Column 1Column 2
Net earnings of $42 million ($33 million after-tax) and $36 million ($29 million after-tax) recorded in 2023 and 2022, related to customer revenues for an EIS insurance contract offset by expected wildfire claims insured by EIS. See "Notes to Consolidated Financial Statements—Note 18. Related-Party Transactions" for further information.

See "Results of Operations" for discussion of SCE and Edison International Parent and Other results of operations.

Electricity Industry Trends

The electric power industry is undergoing urgent and fundamental changes to how energy infrastructure is planned and built, driven by federal and state government actions to reduce GHG emissions, new sources of demand, such as electric vehicles and building electrification, and technological innovations that support clean energy adoption, such as customer-owned generation and energy storage. These factors are altering the way in which electricity is generated and delivered, as well as the regulatory and business environment for the industry.

California is committed to reducing its GHG emissions, improving local air quality and supporting continued economic growth. The state codified into law goals to reduce GHG emissions by 40% from 1990 levels by 2030 and 85% from the same baseline by 2045, as well as to be carbon neutral by 2045. State and local air quality plans also call for substantial

6

Table of Contents

improvements. In the most polluted areas of the state this includes reducing smog-causing nitrogen oxides 90% below 2010 levels by 2032.

While these policy goals cannot be achieved by the electric sector alone, the electric grid is a critical enabler of the adoption of energy technologies that support California's GHG reduction objectives. California has set RPS targets which require California retail sellers of electricity to provide 60% of power from renewable resources by 2030. California also requires sellers of electricity to deliver 100% of retail sales from carbon-free sources by 2045, including interim targets of 90% by 2035 and 95% by 2040. In 2023, approximately 49% of SCE's customer deliveries came from carbon-free resources. SCE remains well-positioned to meet its long-term RPS and carbon-free power goals and interim targets. In addition, Edison International is committed to achieving net-zero GHG emissions by 2045, in alignment with economywide climate actions planned by California. This commitment covers the power SCE delivers to customers and Edison International's enterprise-wide operations.

The current federal administration has also responded to climate change through numerous regulatory and Executive Order actions including for the development of more robust fuel efficiency and vehicle emission standards. Many of these actions align with internal company goals and efforts to address and mitigate climate change. Additionally, building upon the historic infrastructure legislation of 2021, Congress passed the IRA in 2022 that provides significant new funding to electrify the economy. Edison International believes these actions complement its industry-leading efforts to equitably transition to a decarbonized economy.

Edison International believes that California's 2045 goals can be achieved most economically through emissions reductions from using clean electricity to serve 100% of retail sales, electrifying approximately 90% of light-duty vehicles, 90% of medium-duty vehicles, 54% of heavy-duty vehicles, 80% of buses and 95% of buildings and using low-carbon fuels for technologies that are not yet viable for electrification. California has demonstrated strong long-term support of transportation electrification as shown by the approval of SCE's Charge Ready programs and 2022 legislation banning sales of new gas vehicles by 2035. However, Edison International believes that more state policy support, along with public and private investment, is needed to enable California to reach its 2030 and 2045 GHG reduction targets.

To support these goals, Edison International's vision is to lead the transformation of the electric power industry and the company is focused on opportunities in delivering clean energy, advancing electrification, building a modernized and more reliable grid, and enabling customers' technology choices. SCE's ongoing focus to drive operational and service excellence is intended to allow it to achieve these objectives safely while controlling costs and customer rates. SCE projects that, even as electricity bills increase over time, due to higher efficiency of electrified end-use technologies, decarbonization and electrification will reduce total energy consumption costs for the average family by 40% by 2045.

SCE's grid investment is a key enabler of economywide electrification. To support system reliability, SCE is investing $1.0 billion in utility owned storage capacity as well as contracting for substantial new clean energy resources. See "—Capital Program" and "Business—SCE—Purchased Power and Fuel Supply—CAISO Wholesale Energy Market" for further details. SCE also continues to implement its transportation electrification programs. As of December 31, 2023, SCE had completed construction at 259 sites to support 4,425 charge ports under its suite of light-duty Charge Ready programs, and 65 sites to support the electrification of 1,540 medium and heavy-duty vehicles through its Charge Ready Transport program. SCE plans to invest approximately $13 billion in infrastructure replacement between 2023 and 2028 to ensure the grid is reliable, resilient, and ready for widespread electrification. This represents approximately 30% of the capital plan for that same time period, as discussed in "—Capital Program."

SCE and Edison International are investing in building a more resilient grid to reduce climate- and weather-related vulnerabilities. Since 2018, SCE has been adapting to climate change through system hardening to reduce wildfire risk. In its 2025 GRC, SCE proposed climate adaptation investments to address wildfire and physical risks that could occur by 2030.

7

Table of Contents

Changes in the electric power industry are impacting customers and jurisdictions outside California as well. Many other states and countries are also pursuing climate change and GHG reduction objectives and large commercial and industrial customers are continuing to pursue cost reduction and sustainability goals. Edison Energy is a global energy advisory firm providing integrated sustainability and energy solutions to commercial, industrial and institutional customers who may be impacted by these changes.

To better engage in this broader transformation and provide a view of developments outside of SCE, Edison International has also made several investments in emerging companies in areas related to the technology and business model changes that are driving industry transformation and may make additional investments in the future. These investments are not financially material to Edison International.

Track 4

In November 2023, the CPUC approved an all-party settlement in Track 4, which authorized an $8.4 billion revenue requirement for 2024, subject to adjustments for updated operations and maintenance escalation rates, the CPUC's decisions to adopt SCE's 2023 to 2025 cost of capital, and expanded customer-funded self-insurance for wildfire-related claims.

2025 General Rate Case

SCE filed its 2025 GRC application with the CPUC in May 2023, for the four-year period 2025 – 2028. In its application, SCE is requesting that the CPUC authorize SCE's test year 2025 revenue requirement of approximately $10.3 billion. This represents a $1.9 billion, or 23% increase over the approximately $8.4 billion 2024 revenue requirement adopted in Track 4 (prior to adjustments for the CPUC's decisions as discussed above in "—Track 4").

SCE's 2025 GRC request also includes proposed revenue requirement increases of approximately $600 million, $700 million, and $700 million in 2026, 2027 and 2028, respectively.

SCE's 2025 GRC highlights its focus on safely providing electric service to its customers that is reliable, resilient, and ready for their needs today and the clean energy transition directed by California policy. The critical drivers of SCE's 2025 GRC request include returning to historical levels of infrastructure replacement work necessary for system reliability as wildfire mitigation activities stabilize, investments in reliability and capacity upgrades to ready the grid for increased electrification to meet customer needs and California's electrification and decarbonization goals, and investments in programs aimed at protecting the safety of the public, customers and SCE's workforce.

In its application, SCE requested that the CPUC issue a final decision on its application by the end of 2024. If the decision is delayed, SCE will request the CPUC to issue an order directing that the authorized revenue requirement changes be effective January 1, 2025, even if the decision is issued subsequent to that date, consistent with CPUC practice in prior GRCs.

For details of 2024 – 2028 capital program forecast and range case, see "—Capital Program."

8

Table of Contents

Cost of Capital Trigger

The cost of capital adjustment mechanism set by the CPUC provides for an adjustment to SCE's authorized cost of capital that, when triggered, will impact SCE's results of operations and cash flows. In 2023, the cost of capital adjustment mechanism was triggered when the difference between the average Moody's Baa utility bond yield for the 12-month period from October 1, 2022 through September 30, 2023 and the mechanism's benchmark exceeded 100-basis points. As a result, SCE's CPUC-authorized ROE increased from 10.05% to 10.75% effective January 1, 2024. Additionally, SCE's authorized costs of long-term debt and preferred equity for 2024 were updated to 4.48% and 7.02%, respectively. The total resulting increase to SCE's 2024 GRC-related revenue requirement is $201 million, which will be implemented in rates starting in the first quarter of 2024. Certain parties have sought review or suspension of the 2024 adjustment, which could impact SCE's authorized cost of capital for 2024. For further information see "Business—SCE— Overview of Ratemaking Process."

Capital Program

Total capital expenditures (including accruals) were $5.4 billion in 2023 and $5.7 billion in 2022. SCE's year-end rate base was $42.7 billion at December 31, 2023, compared to $40.6 billion at December 31, 2022, after excluding rate base associated with AB 1054 Excluded Capital Expenditures.

SCE's 2023 recorded and 2024 – 2028 forecast capital expenditures are set forth in the table below:

Total
(in billions)2023202420252026202720282024 – 2028
Traditional capital expenditures
Distribution$4.0$4.3$5.2$5.6$5.5$5.5$26.1
Transmission0.20.40.80.91.00.73.8
Generation0.10.20.20.20.20.10.9
Subtotal4.34.96.26.76.76.330.8
Wildfire mitigation-related capital expenditures1.11.11.31.41.51.46.7
Total capital expenditures$5.4$6.0$7.5$8.1$8.2$7.7$37.5
Total capital expenditures using range case discussed below*$5.6$6.6$6.8$6.8$6.4$32.2

*     Not applicable

SCE forecasts a $37.5 billion total capital program for 2024 through 2028, based on the Track 4 settlement (see "—Track 4") and 2025 GRC application, adjusted for ongoing delays in the Riverside Transmission Reliability Project (see "Liquidity and Capital Resources—SCE—Capital Investment Plan") and denial of SCE’s Building Electrification Program (see “Liquidity and Capital Resources—SCE—Regulatory Proceedings”). This forecast includes GRC capital expenditures, CPUC non-GRC capital expenditures, and FERC capital expenditures.

Based on management judgment of potential capital spending variability informed by historical precedent of previously authorized amounts, potential permitting delays and other operational considerations, a range case has been prepared reflecting reductions to GRC capital expenditures, CPUC non-GRC capital expenditures and FERC capital expenditures. Based on the range case, SCE forecasts $32.2 billion total capital expenditures for 2024 through 2028.

In addition to the amounts presented in the table above, SCE expects to make additional CPUC capital investments, the recovery of which will be subject to future regulatory approval. This includes non-GRC programs including additional spending on an enterprise resource planning software implementation, an advanced metering infrastructure program and other potential investments in the grid supporting reliability, resilience and readiness. SCE expects the total expenditures of these programs to be at least $2.0 billion, some of which will be incurred beyond 2028. In addition, in May 2023,

9

Table of Contents

CAISO released its 2022 – 2023 Transmission Plan based on the CPUC's projections that it needs to add more than 40 gigawatts of new resources by 2032. As the incumbent transmission owner for a portion of these transmission projects, SCE expects to construct projects representing at least $2.0 billion of expenditures, most of which will be incurred beyond 2028.

Reflected below is SCE's weighted average annual rate base for 2023 – 2028 incorporating CPUC- and FERC- jurisdictional capital expenditures and planned non-GRC projects or programs.

(in billions)202320242025202620272028
Rate base for expected capital expenditures$41.2$43.4$49.4$53.0$56.8$60.6
Rate base for expected capital expenditures using range case discussed above*$43.0$48.1$50.4$52.8$55.3

*     Not applicable

SCE forecasts total weighted-average rate base incorporating CPUC- and FERC-jurisdictional capital expenditures increasing to $60.6 billion by 2028 based on the Track 4 settlement and 2025 GRC application adjusted for delays in the utility owned storage projects, the Riverside Transmission Reliability Project, and a reduction of working capital following implementation of the customer-funded self-insurance program.

Southern California Wildfires and Mudslides

California has experienced unprecedented weather conditions in recent years due to climate change. The worsening weather and fuel conditions across California increase the likelihood of wildfires, including those where SCE's equipment may be alleged to be associated with the fire's ignition, and SCE's service territory remains susceptible to additional wildfire activity in 2024 and beyond.

Wildfires in SCE's territory have caused loss of life, substantial damage to both residential and business properties, and service outages for SCE customers. SCE's equipment has been, and may further be, alleged to be associated with wildfires that originate in Southern California.

In response to worsening conditions and wildfire activity in its territory in the recent past, SCE has developed and is implementing its WMP to reduce the risk of SCE equipment contributing to the ignition of wildfires. In addition, California has increased its investment in wildfire prevention and fire suppression capabilities. Further to the investments SCE is making as part of its WMP, SCE also uses its PSPS program to proactively de-energize power lines as a last resort to mitigate the risk of significant wildfires during extreme weather events.

2017/2018 Wildfire/Mudslide Events

Multiple lawsuits and investigations related to the 2017/2018 Wildfire/Mudslide Events have been initiated against SCE and Edison International and SCE has incurred material losses in connection with the 2017/2018 Wildfire/Mudslide Events.

SCE has previously entered into settlements with a number of local public entities and subrogation plaintiffs in the TKM and Woolsey litigations and under the SED Agreement. In addition, SCE has also entered into settlements with approximately 12,000 individual plaintiffs in the 2017/2018 Wildfire/Mudslide Events litigation.

In 2023, SCE accrued estimated losses of $630 million for remaining alleged and potential claims related to the 2017/2018 Wildfire/Mudslide Events. As a result, SCE also recorded expected recoveries through FERC electric rates of $37 million against the charge, and the resulting net charge to earnings was $593 million ($428 million after-tax).

Through December 31, 2023, SCE has accrued estimated losses of $9.4 billion, recoveries from insurance of $2.0 billion, all of which have been collected, and expected recoveries through FERC electric rates of $413 million,

10

Table of Contents

$376 million of which has been collected, related to the 2017/2018 Wildfire/Mudslide Events claims. The after-tax net charges to earnings recorded for claims related to the 2017/2018 Wildfire/Mudslide Events through December 31, 2023 have been $5.1 billion.

Estimated losses for the 2017/2018 Wildfire/Mudslide Events litigation are based on a number of assumptions and are subject to change as additional information becomes available. Actual losses incurred may be higher or lower than estimated based on several factors, including the uncertainty in estimating damages that have been or may be alleged. For instance, SCE receives additional information with respect to damages claimed as the claims mediation and trial processes progress. Other factors that can cause actual losses incurred to be higher or lower than estimated include the ability to reach settlements and the outcomes of settlements reached through the ongoing claims mediation processes, uncertainties related to the sufficiency of insurance held by plaintiffs, uncertainties related to the litigation processes, including whether plaintiffs will ultimately pursue claims, uncertainty as to the legal and factual determinations to be made during litigation, including uncertainty as to the contributing causes of the 2017/2018 Wildfire/Mudslide Events, the complexities associated with fires that merge and whether inverse condemnation will be held applicable to SCE with respect to damages caused by the Montecito Mudslides, and the uncertainty as to how these factors impact future settlements.

As of December 31, 2023, SCE had paid $8.7 billion under executed settlements and had $78 million to be paid under executed settlements, including $62 million to be paid under the SED Agreement, related to the 2017/2018 Wildfire/Mudslide Events. After giving effect to all payment obligations under settlements entered into through December 31, 2023, Edison International's and SCE's best estimate of expected losses for remaining alleged and potential claims related to the 2017/2018 Wildfire/Mudslide Events was $637 million. Edison International and SCE may incur a material loss in excess of amounts accrued in connection with the remaining alleged and potential claims related to the 2017/2018 Wildfire/Mudslide Events.

SCE will seek CPUC-jurisdictional rate recovery of prudently-incurred losses and related costs realized in connection with the 2017/2018 Wildfire/Mudslide Events in excess of available insurance and FERC-jurisdictional recoveries, other than for any obligations under the SED Agreement. Based on Edison International's and SCE's current best estimate of expected losses for the 2017/2018 Wildfire/Mudslide Events, SCE currently expects to seek CPUC-jurisdictional rate recovery of approximately $6.4 billion of uninsured claims by filing applications with the CPUC. In August 2023, SCE filed the first of such cost recovery applications to seek rate recovery of $2.4 billion of prudently incurred losses related to the Thomas Fire, the Koenigstein Fire and the Montecito Mudslides, consisting of $2.0 billion of uninsured claims and $0.4 billion of associated costs, including legal fees and financing costs. In its filing, SCE is also seeking capital recovery of approximately $65 million in restoration costs. SCE has requested that the CPUC issue a proposed decision on its application in February 2025. SCE targets the third quarter of 2024 for the filing of its application to seek rate recovery of approximately $4 billion of uninsured claims related to the Woolsey Fire. In its application, SCE will also seek associated costs, including legal fees, financing costs and restoration costs. SCE's plans with respect to this filing may be delayed or modified. Because the CPUC's decision in a cost recovery proceeding involving SDG&E arising from several 2007 wildfires in SDG&E's service area is the only directly comparable precedent available, SCE believes that there is substantial uncertainty regarding how the CPUC will interpret and apply its prudency standard to an investor-owned utility in wildfire claims related cost-recovery proceedings for fires ignited prior to the adoption of AB 1054 on July 12, 2019. Accordingly, while the CPUC has not made a determination regarding SCE's prudency relative to any of the 2017/2018 Wildfire/Mudslide Events, SCE is unable to conclude, at this time, that uninsured CPUC-jurisdictional wildfire-related costs related to the 2017/2018 Wildfire/Mudslide Events are probable of recovery through electric rates.

2017 Creek Fire

In addition to the Thomas, Koenigstein and Woolsey Fires, there were several other wildfires ignited in 2017 and 2018 that impacted portions of SCE's service territory, including the 2017 Creek Fire that ignited near Sylmar, California.

11

Table of Contents

Based on pending litigation, it is reasonably possible that SCE will incur a material loss in connection with the Creek Fire, but the range of reasonably possible losses that could be incurred cannot be estimated at this time. SCE has not determined that losses in connection with the Creek Fire are probable and consequently has not accrued a charge for potential losses relating to the Creek Fire. SCE’s wildfire insurance for the period in which the Creek Fire was ignited has been almost fully exhausted as a result of the TKM litigation.

Post-2018 Wildfires

Several wildfires have significantly impacted portions of SCE's service territory after 2018, including the 2019 Saddle Ridge Fire, the 2020 Bobcat Fire, the 2022 Coastal Fire and the 2022 Fairview Fire.

In 2023, SCE recorded a $184 million increase in estimated losses for claims related to the Post-2018 Wildfires and recorded $149 million in expected insurance recoveries against the charge. As a result, SCE also recorded expected recoveries through electric rates of $2 million against the charges accrued related to the Post-2018 Wildfires. The resulting net charge to earnings was $33 million ($24 million after-tax).

Through December 31, 2023, SCE has recorded total estimated losses of $880 million and expected recoveries from insurance and third parties of $622 million related to the Post-2018 Wildfire claims. As a result, SCE also recorded expected recoveries through electric rates of $168 million against the charges accrued related to the Post-2018 Wildfire claims. The after-tax net charges to earnings recorded through December 31, 2023 have been $65 million.

As of December 31, 2023, SCE had paid $204 million under executed settlements related to the Post-2018 Wildfires, and Edison International's and SCE's estimated losses for remaining alleged and potential claims (established at the low end of the estimated range of reasonably possible losses) related to the Post-2018 Wildfires was $676 million. As of the same date, SCE had assets for expected recoveries through insurance and third parties of $512 million and through electric rates of $154 million on its consolidated balance sheets related to the Post-2018 Wildfire claims.

While Edison International and SCE may incur material losses in excess of the amounts accrued for certain of the Post-2018 Wildfires, Edison International and SCE expect that any losses incurred in connection with any such fire will be covered by insurance, subject to self-insured retentions and co-insurance, and expect that any losses after expected recoveries from insurance and through electric rates will not be material.

In light of the prudency standard the CPUC is required to apply under AB 1054 to utilities holding a safety certificate at the time a wildfire ignited after July 12, 2019, SCE has concluded, at this time, that both uninsured CPUC-jurisdictional and uninsured FERC-jurisdictional wildfire-related costs related to the Post-2018 Wildfires that it has deferred as regulatory assets are probable of recovery through electric rates. SCE will continue to evaluate the probability of recovery based on available evidence, including regulatory decisions, including any CPUC decisions illustrating the interpretation and/or application of the prudency standard under AB 1054, and, for each applicable fire, evidence that could cast serious doubt as to the reasonableness of SCE's conduct relative to that fire.

For further information on Southern California Wildfires and Mudslides, see "Business— Southern California Wildfires," "Risk Factors," "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—Initial and annual contributions to the wildfire insurance fund established pursuant to California Assembly Bill 1054" and "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides" in this report.

Customer-Funded Self-Insurance

In May 2023, the CPUC approved a joint petition for modification of the 2021 GRC decision filed by SCE, The Utility Reform Network and the Public Advocates Office, allowing SCE to expand its use of self-insurance. The approved self-insurance program is effective for wildfires ignited between July 1, 2023 and December 31, 2024, and has been funded

12

Table of Contents

through CPUC-jurisdictional rates with $150 million collected during the second half of 2023 and, in the absence of wildfire-related claims, $300 million to be collected in 2024. The self-insurance program resulted in a reduction to current revenue requirements of $80 million in 2023 and, subject to adjustment, $160 million in 2024. If losses are accrued for wildfire-related claims, the program contains an adjustment mechanism that will increase rates in subsequent years as needed, to allow for full recovery of the amounts accrued up to $1.0 billion per policy year, subject to a shareholder contribution of 2.5% of any self-insurance costs ultimately paid exceeding $500 million in any policy year, up to a maximum annual contribution of $12.5 million per policy year. If adopted in the 2025 GRC, this self-insurance framework will continue at least through 2028, supporting a self-insurance fund of up to $1.0 billion per policy year. SCE expects continuation of the customer-funded self-insurance framework to be adopted without protest in the 2025 GRC. Depending upon losses over time, customers will benefit further from SCE's wildfire self-insurance program as a result of not having to fund the recurring costs of SCE purchasing commercial wildfire insurance coverage.

RESULTS OF OPERATIONS

SCE

SCE's results of operations are derived mainly through two sources:

Column 1Column 2
Earning activities – representing revenue authorized by the CPUC and the FERC, which is intended to provide SCE with a reasonable opportunity to recover its costs and earn a return on its net investment in generation, transmission, and distribution assets. The annual revenue requirements are comprised of authorized operation and maintenance costs, depreciation, taxes and a return consistent with the capital structure. Also, included in earnings activities are revenue or penalties related to incentive mechanisms, other operating revenue and regulatory charges or disallowances.
Column 1Column 2
Cost-recovery activities – representing CPUC- and FERC-authorized balancing accounts which allow for recovery of specific project or program costs, subject to reasonableness review or compliance with upfront standards, as well as non-bypassable rates collected for SCE Recovery Funding LLC. Cost-recovery activities include rates which provide recovery, subject to reasonableness review of, among other things, fuel costs, purchased power costs, public purpose related-program costs (including energy efficiency and demand-side management programs), certain operation and maintenance expenses, (including vegetation management and wildfire insurance), and repayment of bonds and financing costs of SCE Recovery Funding LLC. SCE earns no return on these activities.

13

Table of Contents

Years ended December 31, 2023, 2022 and 2021

The following table is a summary of SCE's results of operations for the periods indicated:

202320222021
Cost-Cost-Cost-
EarningRecoveryTotalEarningRecoveryTotalEarningRecoveryTotal
(in millions)ActivitiesActivitiesConsolidatedActivitiesActivitiesConsolidatedActivitiesActivitiesConsolidated
Operating revenue$9,012$7,263$16,275$9,008$8,164$17,172$7,872$7,002$14,874
Purchased power and fuel5,4865,4866,3756,3755,5405,540
Operation and maintenance2,3111,7604,0712,7931,8664,6592,0151,5733,588
Wildfire-related claims, net of insurance recoveries6656651,3051,3051,2761,276
Wildfire Insurance Fund expense213213214214215215
Depreciation and amortization2,588452,6332,540192,5592,20972,216
Property and other taxes5392756648215497462462
Impairment, net of other operating income(2)3150506767
Total operating expenses6,3147,32113,6357,3848,27515,6596,2447,12013,364
Operating income (loss)2,698(58)2,6401,624(111)1,5131,628(118)1,510
Interest expense(1,312)(44)(1,356)(977)(28)(1,005)(785)(6)(791)
Other income, net395102497198139337109124233
Income before income taxes1,7811,781845845952952
Income tax expense (benefit)184184(109)(109)1717
Net income1,5971,597954954935935
Preference stock dividend requirements123123107107106106
Net income available for common stock$1,474$$1,474$847$$847$829$$829

Earning Activities

Earning activities in 2023 compared to 2022 were primarily affected by the following:

Column 1Column 2
Higher operating revenue of $4 million is primarily due to:
Column 1Column 2Column 3
An increase of CPUC-related revenue of $411 million due to the escalation mechanism set forth in the 2021 GRC decision.
Column 1Column 2Column 3
A decrease of CPUC-related revenue of $358 million due to lower wildfire-related expenses that had been

authorized for recovery during 2022 through Track 2 and Track 3.

Column 1Column 2Column 3
A decrease of CPUC-related revenue of $49 million related to lower CSRP revenue requirements approved in 2023 than in 2022.
Column 1Column 2
Lower operation and maintenance costs of $482 million primarily due to the following:
Column 1Column 2Column 3
In 2022, SCE recognized $404 million of previously deferred wildfire-related expenses upon approval of Track 2 and Track 3, compared to $54 million previously deferred expenses recognized in 2023 primarily related to the Track 3 in 2023. These wildfire-related expenses were offset in revenue.
Column 1Column 2Column 3
In 2022, SCE recognized a charge of $95 million related to the POD on SCE's Upstream Lighting Program. This consisted of $76 million of disallowed costs reclassified from cost recovery activities and $19 million of fines.

14

Table of Contents

Column 1Column 2Column 3
Lower uncollectible expenses of $40 million primarily due to prior period expenses not subject to cost recovery recorded in 2022. A CPUC decision in 2022 required SCE to change its methodology for calculating the portion of uncollectible expenses incremental to GRC authorized revenues.
Column 1Column 2Column 3
In 2023, SCE recognized a probable disallowance of $30 million related to the 2021 NDCTP. See "Liquidity and Capital Resources—SCE—Decommissioning of San Onofre" for more information.
Column 1Column 2
Wildfire-related claim charges were $665 million and $1.3 billion in 2023 and 2022, respectively, primarily related to the 2017/2018 Wildfire/Mudslide Events. See "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."
Column 1Column 2
Higher depreciation and amortization expense of $48 million primarily due to increased plant balances, partially offset by the CSRP decision received in 2022, which authorized SCE to recover $134 million of previously deferred depreciation expense.
Column 1Column 2
Higher property and other taxes of $57 million primarily due to higher property assessed value in 2023.
Column 1Column 2
Impairments were recorded in 2022, of which $17 million related to the CPUC decision in Track 3 and $47 million related to a settlement agreement between SCE and TURN in the CSRP proceeding during 2022.
Column 1Column 2
Higher interest expense of $335 million primarily due to higher interest rates on long-term debt, short-term debt and balancing account overcollections, as well as increased long-term borrowings.
Column 1Column 2
Higher other income of $197 million primarily due to higher interest rates applied to balancing account undercollections.
Column 1Column 2
See "Income Taxes" below for the explanation of $293 million increase in income tax expenses.
Column 1Column 2
Higher preference stock dividend requirements of $16 million primarily due to dividends paid on Series E preference stock at a higher rate. See "Notes to Consolidated Financial Statements—Note 14. Equity— Preferred and Preference Stock of Utility."

Cost-Recovery Activities

Cost-recovery activities in 2023 compared to 2022 were primarily affected by the following:

Column 1Column 2
Lower purchased power and fuel costs of $889 million, primarily due to lower prices and volumes for both purchased power and gas, partially offset by hedging activities.
Column 1Column 2
Lower operation and maintenance costs of $106 million primarily due to:
Column 1Column 2Column 3
Lower insurance costs of $218 million due to expansion of SCE's use of customer-funded self-insurance for wildfire-related claims in July 2023.
Column 1Column 2Column 3
A net decrease of $114 million due to lower recognition of previously deferred expenses primarily related to wildfire mitigation, drought restoration, and COVID-19.
Column 1Column 2Column 3
Lower uncollectible expenses of $79 million primarily due to the recognition of $109 million previously deferred uncollectible expenses in the first quarter of 2022.
Column 1Column 2Column 3
In 2023, SCE recognized $209 million of previously deferred incremental wildfire insurance premiums that provided coverage for the last six months of 2020.

15

Table of Contents

Column 1Column 2Column 3
$76 million of disallowed costs were reclassified to earnings activities related to Upstream Lighting Program in 2022. See "—Earnings Activities" above.
Column 1Column 2
Higher amortization expense, property and other taxes and interest expenses of $26 million, $12 million, and $16 million, respectively, primarily due to recovery of expenses associated with AB 1054 Excluded Capital Expenditures financed through securitization.
Column 1Column 2
Lower other income of $37 million primarily driven by lower net periodic benefit income related to the non-service cost components for SCE's pension and PBOP. See "Notes to Consolidated Financial Statements—Note 9. Compensation and Benefit Plans" for further information.

Supplemental Operating Revenue Information

As a result of the CPUC-authorized decoupling mechanism, SCE revenues are not affected by changes in retail electricity sales.

Income Taxes

Higher income tax expense of $293 million in 2023 compared to 2022 (a tax benefit was recorded in 2022) was primarily driven by the increase in pre-tax income and lower tax benefit associated with CSRP revenue recovery in 2023. The effective tax rates were 10.3% and (12.9)% for 2023 and 2022, respectively. SCE's effective tax rate is below the federal statutory rate of 21% for 2023 and 2022 primarily due to the CPUC's ratemaking treatment for the current tax benefit arising from certain property-related and other temporary differences, which reverse over time. The accounting treatment for these temporary differences results in recording regulatory assets and liabilities for amounts that would otherwise be recorded to deferred income tax expense.

See "Notes to Consolidated Financial Statements—Note 8. Income Taxes" for a reconciliation of the federal statutory rate to the effective income tax rates.

Edison International Parent and Other

Results of operations for Edison International Parent and Other include amounts from other subsidiaries that are not reportable as segments, as well as intercompany eliminations.

Loss from Operations

The following table summarizes the results of Edison International Parent and Other:

Years ended December 31,
(in millions)202320222021
Edison Energy Group, Inc. (a subsidiary of Edison International) and subsidiaries$(12)$(17)$(15)
Corporate expenses and other subsidiaries(178)(113)5
Edison International Parent and Other net loss$(190)$(130)$(10)
Less: Preferred stock dividend requirements8710560
Edison International Parent and Other net loss attributable to common shareholders$(277)$(235)$(70)

16

Table of Contents

The net loss attributable to common shareholders from operations of Edison International Parent and Other increased $42 million in 2023 compared to 2022 primarily due to higher interest expense, partially offset by gains on preferred stock repurchases of $16 million.

LIQUIDITY AND CAPITAL RESOURCES

SCE

SCE's ability to operate its business, fund capital expenditures, and implement its business strategy is dependent upon its cash flow and access to the bank and capital markets. SCE's overall cash flows fluctuate based on, among other things, its ability to recover its costs in a timely manner from its customers through regulated rates, changes in commodity prices and volumes, collateral requirements, interest obligations, dividend payments to and equity contributions from Edison International, obligations to preference shareholders, and the outcome of tax, regulatory and legal matters.

In the next 12 months, SCE expects to fund its cash requirements through operating cash flows, and capital market and bank financings. SCE also has availability under its credit facility to fund cash requirements. SCE also expects to issue additional debt for general corporate purposes, and to finance and refinance debt issued for payment of claims and expenses related to the 2017/2018 Wildfire/Mudslide Events.

SCE issued securitized bonds in the amounts of $775 million, $533 million, and $338 million in 2023, 2022, and 2021, respectively, to finance the required AB 1054 Excluded Capital Expenditures and related financing costs. For more information, see "Notes to Consolidated Financial Statements––Note 5. Debt and Credit Agreements."

The following table summarizes SCE's current long-term issuer credit ratings and outlook from the major credit rating agencies:

Moody'sFitchS&P
Credit RatingBaa1BBBBBB
OutlookStableStableStable

SCE's credit ratings may be affected if, among other things, regulators fail to successfully implement AB 1054 in a consistent and credit supportive manner, or the Wildfire Insurance Fund is depleted by claims from catastrophic wildfires. Credit rating downgrades increase the cost and may impact the availability of short-term and long-term borrowings, including commercial paper, credit facilities, bond financings or other borrowings. In addition, some of SCE's power procurement contracts and environmental remediation obligations would require SCE to pay related liabilities or post additional collateral if SCE's credit rating were to fall below investment grade. For further details, see "—Margin and Collateral Deposits."

For restrictions on SCE's ability to pay dividends, see "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—SCE Dividends."

Available Liquidity

At December 31, 2023, SCE had cash on hand of $214 million and approximately $1.8 billion available to borrow on its $3.4 billion revolving credit facility. The credit facility is available for borrowing needs until May 2027. The aggregate maximum principal amount under the SCE revolving credit facility may be increased up to $4.0 billion, provided that additional lender commitments are obtained. SCE also has standby letters of credit with total capacity of $625 million, and the unused amount was $572 million as of December 31, 2023. For further details, see "Notes to Consolidated Financial Statements—Note 5. Debt and Credit Agreements."

At December 31, 2023, SCE had $1.6 billion outstanding commercial paper, net of discount, at a weighted average interest rate of 5.82%. In January 2024, SCE issued $500 million and $900 million of first and refunding mortgage

17

Table of Contents

bonds due in 2027 and 2034, respectively. The proceeds were used to repay part of the commercial paper borrowings outstanding as of December 31, 2023, fund the payment of wildfire claims and related expenses above insurance proceeds, and for general corporate purposes.

SCE may finance balancing account undercollections and working capital requirements to support operations and capital expenditures with commercial paper, its credit facilities or other borrowings, subject to availability in the bank and capital markets. As necessary, SCE will utilize its available liquidity, capital market financings, other borrowings or parent company contributions to SCE equity in order to meet its obligations as they become due, including costs related to the 2017/2018 Wildfire/Mudslide Events. For further information, see "Management Overview—Southern California Wildfires and Mudslides."

Debt Covenant

SCE's credit facilities and term loan require a debt to total capitalization ratio as defined in the applicable agreements of less than or equal to 0.65 to 1. At December 31, 2023, SCE's debt to total capitalization ratio was 0.56 to 1.

At December 31, 2023, SCE was in compliance with all financial covenants that affect access to capital.

Regulatory Proceedings

Wildfire Related Regulatory Proceedings

In response to the increase in wildfire activity, and faster progression of and increased damage from wildfires across SCE's service territory and throughout California, SCE has incurred wildfire mitigation, wildfire insurance and wildfire and drought restoration related spending at levels significantly exceeding amounts authorized in SCE's GRCs.

2021 GRC Wildfire Mitigation Memorandum Account Balances

The 2021 GRC decision authorized the establishment of balancing accounts for expenses for vegetation management, wildfire insurance, and the WCCP program, with expenditures up to certain thresholds approved for cost recovery. SCE may submit subsequent reasonableness review applications for any spending in excess of these thresholds. SCE has incurred vegetation management expenses and capital expenditures for WCCP in excess of thresholds established in the 2021 GRC. SCE has also incurred costs in excess of amounts authorized in the 2021 GRC related to other wildfire mitigation activities, including inspections and maintenance and to support execution of PSPS events.

In June 2022, SCE filed an application with the CPUC requesting reasonableness review of the incremental costs incurred in 2021 related to non-WCCP wildfire mitigation and vegetation management activities, requesting a total revenue requirement of approximately $327 million. In February 2024, the CPUC issued a proposed decision that, if adopted, will authorize a total revenue requirement of $310 million, along with ongoing capital revenue requirements and interest. These revenue requirements will be amortized over 12 months.

In October 2023, SCE requested authority to recover revenue requirements associated with 2022 operations and maintenance and capital expenditures above levels authorized in wildfire mitigation accounts and the vegetation management balancing account. The revenue requirement, including interest, is currently estimated at $384 million. In January 2024, SCE filed a supplemental motion for interim rate recovery to include $210 million of these costs and associated interest in revenue requirements beginning March 1, 2024.

2020 Emergency Wildfire Restoration

Multiple wildfires occurred during 2020 which caused damage within SCE's service territory and to SCE's Big Creek hydroelectric facility.

In March 2022, SCE filed a catastrophic event memorandum account application requesting recovery of $207 million of

18

Table of Contents

operation and maintenance expenses incremental to authorized revenue requirements and $312 million of capital expenditures incremental to amounts authorized in the 2021 GRC primarily related to these restoration efforts. SCE has not yet filed for recovery of generation restoration costs, as repairs to hydroelectric generation facilities are not complete.

2024 FERC Formula Rate Annual Update

In November 2023, SCE filed its 2024 annual transmission revenue requirement update with the FERC, with the rate effective January 1, 2024. The update reflects a $1.1 billion transmission revenue requirement for 2024, $290 million or 20% lower than amounts included in the 2023 annual rates. The decrease is primarily due to returning an overcollection based on actual 2022 costs and lower wildfire-related claims.

Building Electrification Programs Application

In December 2021, SCE filed a $677 million Building Electrification Program Application for a four-year program (2024 – 2027) to incentivize replacing 250,000 gas-fueled water and space heaters with efficient electric heat pumps and to upgrade or enhance the electrical infrastructure for 65,000 homes to support electrification. The proposed program included $200 million for customer-side electrical infrastructure upgrades for which SCE requested inclusion as a regulatory asset in rate base, $69 million in capital expenditures and $408 million of operations and maintenance expense including heat pump incentives, program administration, and implementation costs. In January 2024, the CPUC issued a decision denying the application in its entirety.

Capital Investment Plan

Major Transmission Projects

A summary of SCE's most significant transmission and substation construction projects during the next two years is presented below. The timing of the projects below is subject to timely receipt of permitting, licensing and regulatory approvals.

Direct
ProjectExpendituresInception to DateScheduled In-
Project NameLifecycle Phase(in millions)1(in millions)1Service Date
Riverside Transmission Reliability2Licensing584342028
Alberhill System3Licensing472472029
Eldorado-Lugo-Mohave UpgradeConstruction3832472024
Column 1Column 2
1Direct expenditures include direct labor, land and contract costs incurred for the respective projects and exclude overhead costs that are included in the capital expenditures forecast discussed in "Management Overview—Capital Program."
Column 1Column 2
2Expenditures and in-service date are based on CPUC approved plans and will likely be impacted by the timing of CPUC determination of the City of Norco’s petition for modification ("PFM") and any changes to those plans required by Riverside City Council ("RCC").
Column 1Column 2
3In June 2023, SCE filed an amended application for a certificate of public convenience and necessity ("CPCN") with technical design modifications and engineering refinements to the proposed project that decreases project costs and reduces GHG emissions. Accordingly, the direct expenditures of the project are estimated to be reduced from $486 million to $472 million. SCE is unable to predict the timing of a final CPUC decision and the final project costs for the Alberhill System Project.

Riverside Transmission Reliability Project

The Riverside Transmission Reliability Project is a joint project between SCE and Riverside Public Utilities ("RPU"), the municipal utility department of the City of Riverside. While RPU will be responsible for constructing some of the project's facilities within Riverside, SCE's portion of the project consists of constructing upgrades to its system, including a new 230 kV substation; certain interconnection and telecommunication facilities and overhead transmission

19

Table of Contents

lines in the cities of Riverside, Jurupa Valley and Norco and in portions of unincorporated Riverside County. In May 2022, the RCC voted to investigate alternatives to the CPUC approved project. Consequently, SCE suspended all major activities on the project. In January 2023, the RCC voted to establish a working group to pursue funding for additional undergrounding. On October 2, 2023, the City of Norco filed a PFM to modify the CPUC decision approving the project and reopen the record to reconsider full undergrounding. In November 2023, SCE filed a response opposing the PFM.

Alberhill System Project

The Alberhill System Project consists of constructing a new 500 kV substation, two 500 kV transmission lines to connect the proposed substation to the existing Serrano-Valley 500 kV transmission line, telecommunication equipment and subtransmission lines in western Riverside County. The project was designed to meet long-term forecasted electrical demand in the proposed Alberhill System Project area and to increase electrical system reliability and resiliency. In April 2018 and July 2018, the CPUC issued a proposed decision and an alternate proposed decision, both denying SCE's ability to construct the Alberhill System Project based on a perceived lack of need. SCE filed comments on both proposed decisions requesting that the CPUC grant the CPCN for the Alberhill System Project. In August 2018, the CPUC issued a decision that did not deny or approve the Alberhill System Project but directed SCE to submit supplemental information on the Alberhill System Project including but not limited to a load forecast and cost benefit analysis of several alternatives to the proposed project. Ongoing capital spending has been deferred as a result of the CPUC request for additional information. In January 2020, SCE submitted a supplemental analysis to the CPUC for the Alberhill System Project including several alternatives to the proposed project as well as an update to the original project cost. A final decision on the Alberhill System Project remains pending. In June 2023, SCE filed an amended CPCN with technical design modifications and engineering refinements to the proposed project that decrease project costs and reduce GHG emissions. Given the uncertainty associated with the resolution of the permitting process, potential revisions to the project have not been reflected in total direct expenditures. SCE continues to believe a system solution is needed for the project area but is unable to predict the timing of a final CPUC decision in connection with the Alberhill System Project proceeding.

Approximately 48% of the Alberhill System Project costs spent to date would be subject to recovery through CPUC revenue and 52% through FERC revenue. In October 2017, SCE obtained approval from the FERC for abandoned plant treatment for the Alberhill System Project, which allows SCE to seek recovery of 100% of all prudently incurred costs after the approval date and 50% of prudently incurred costs prior to the approval date. Excluding land costs, which may be recovered through sale to a third party, SCE has incurred approximately $62 million of capital expenditures, including overhead costs, of which approximately $44 million may not be recoverable if the project is cancelled as of December 31, 2023.

Eldorado-Lugo-Mohave Upgrade Project

The Eldorado-Lugo-Mohave Upgrade Project will increase capacity on existing transmission lines to allow additional renewable energy to flow from Nevada to southern California. The project would modify SCE's existing Eldorado, Lugo, and Mohave electrical substations to accommodate the increased power flows from Nevada to southern California; increase the power flow through the existing 500 kV transmission lines by constructing two new capacitors along the lines; raise transmission tower heights to meet ground clearance requirements; and install fiber optics on the transmission lines to provide communications between existing SCE substations. In August 2020, the CPUC approved the CPCN for the project.

Construction for the project began in November 2020. The total costs for the Eldorado-Lugo-Mohave Upgrade Project are expected to exceed amounts currently approved in the CPCN granted by the CPUC due to delays in regulatory approvals, contractor performance issues, supply chain constraints, COVID-19 impacts and the availability of CAISO outage windows. In May 2023, SCE filed a Petition for Modification of the decision that approved the project to increase the maximum reasonable and prudent cost for the project, which increased the direct expenditures from $247 million to

20

Table of Contents

$319 million. SCE expects the project to be in service in 2024. Additional work after the in-service date is also required to mitigate the impact of the project on nearby natural gas transmission lines. Current estimation of the additional work is approximately $64 million. A further Petition for Modification is expected to be filed before the authorized spending is exceeded.

Utility Owned Storage Projects

In October 2021, SCE contracted with Ameresco, Inc. ("Ameresco") for the construction of utility owned energy storage projects at three sites in SCE's service territory with an aggregate capacity of 537.5 MW, consisting of a 225 MW project, a 200 MW project and a 112.5 MW project, and an in-service date of August 1, 2022. Ameresco has advised SCE that it currently expects all three projects to be in-service prior to June 2024.

In April 2022, SCE received a force majeure event notice from Ameresco in which Ameresco asserted that both manufacturing delays related to COVID-19 shut-downs in China and new shipping restrictions imposed by Chinese governmental authorities were then impacting the supply of batteries from China necessary for timely completion of the projects. Ameresco subsequently supplemented its force majeure notice noting additional supply chain issues related to COVID-19. Permitting delays and engineering issues and certain changes requested by SCE also impacted the projects in 2022. SCE expects to receive in aggregate approximately $270 million of tax credits available under the IRA for all three projects, which will accrue to the benefit of its customers. In January 2023, SCE received a force majeure event notice from Ameresco in which Ameresco asserted that severe winter storms in Southern California had impacted the timely completion of the projects.

In April 2023, Ameresco discovered damage to some of the equipment at the 225 MW project. Ameresco has sent SCE a notice of potential force majeure event and has concluded that the damage was caused by soil heave and that the soil heave was caused by extreme rainstorms at the project site in the winter of 2022 – 2023. Ameresco is performing corrective action in response to the damage discovered in 2023.

SCE is continuing to evaluate the force majeure event notices and is awaiting additional information from Ameresco on the underlying events. If there is a valid force majeure event under the contracts with Ameresco, subject to certain conditions, the project schedules and any related triggers of liquidated damages may be extended, and the contract prices may be increased to account for the impact of the force majeure event. Because Ameresco did not achieve an in-service date of August 1, 2022, SCE is entitled to liquidated damages under the terms of the contracts subject to any relief Ameresco may be entitled to under the contracts, including any relief for any valid force majeure events. Once triggered, liquidated damages accrue daily for up to 60 days up to a maximum of $89 million in aggregate for all three projects.

Subject to reductions for any liquidated damages SCE is paid, SCE currently expects these storage projects to result in $1.0 billion of capital expenditures. In December 2021, the CPUC approved recovery of these expenditures and establishment of a balancing account for the associated revenue requirement, which have been reflected in rates beginning in the first quarter of 2022. Authorized revenue requirements will be included in the annual ERRA review proceeding and can only be disallowed upon a finding that SCE failed to prudently administer the contracts.

Ameresco has obtained surety bonds to secure its obligations to complete the construction of the projects, and is also required to obtain surety bonds or letters of credit after completion of the projects to secure its performance obligations, including its warranty obligations. If Ameresco is unable to fulfill its obligations and the amounts available under any surety bonds or letters of credit are insufficient or the issuer of any such surety bonds or letters of credit disputes coverage or otherwise does not perform or pay for the performance of Ameresco’s obligations, SCE will incur additional costs beyond its contractual obligations.

21

Table of Contents

Other Capital Investment Projects and Programs

For a discussion of forecast wildfire mitigation capital expenditures, including the WCCP, see "Management Overview—Capital Program." For discussion of Electrification and Clean Energy Transition Programs, see "— Regulatory Proceedings—Building Electrification Programs Application."

Decommissioning of San Onofre

The decommissioning of a nuclear plant requires the management of three related activities: radiological decommissioning, non-radiological decommissioning and the management of spent nuclear fuel. SCE is the operating agent of San Onofre and has engaged the DGC to undertake a significant scope of decommissioning activities for Units 1, 2 and 3 at San Onofre. The decommissioning of San Onofre is expected to take many years. SCE funds decommissioning costs, including costs associated with storing spent nuclear fuel, with assets that are currently held in nuclear decommissioning trusts.

Under federal law, the U.S. Department of Energy ("DOE") is responsible for the selection and construction of a facility for the permanent disposal of spent nuclear fuel and high-level radioactive waste. The DOE has not met its contractual obligation to accept spent nuclear fuel. Extended delays by the DOE have led to the construction of costly alternatives and associated siting and environmental issues. Two Independent Spent Fuel Storage Installations ("ISFSI") store nuclear fuel onsite at San Onofre. The first primarily stores nuclear fuel from Unit 1 ("ISFSI 1") and the second stores nuclear fuel from Units 2 and 3 ("ISFSI 2").

SCE's Coastal Development Permits, the principal discretionary permits required for major decommissioning activities, extend through 2035.

Decommissioning of San Onofre Unit 1 began in 1999 and the transfer of spent nuclear fuel from Unit 1 to dry cask storage in ISFSI 1 was completed in 2005. Major decommissioning work for Unit 1 has been completed except for certain underground work.

Decommissioning of San Onofre Units 2 and 3 began in June 2013 and the transfer of spent nuclear fuel from San Onofre Units 2 and 3 to dry cask storage in the two ISFSIs was completed in August 2020. In August 2020, SCE commenced, and is currently conducting, major decommissioning activities in accordance with the terms of the Coastal Developmental Permit for San Onofre Units 2 and 3.

In 2021, SCE updated its decommissioning cost estimate for decommissioning activities to be completed at San Onofre Units 2 and 3 to $3.4 billion (SCE share is $2.6 billion) in 2021 dollars. The decommissioning cost estimate included costs through the expected decommissioning completion date, currently estimated to be in 2053 for San Onofre Units 2 and 3. SCE requested approval of its updated decommissioning cost estimate from the CPUC in February 2022 as part of its 2021 NDCTP filing. Decommissioning cost estimates are subject to a number of uncertainties including the cost and timing of nuclear waste disposal, the time it will take to obtain required permits, cost of removal of property, site remediation costs, as well as a number of other assumptions and estimates, including when the federal government will provide for either interim or permanent off-site storage of spent nuclear fuel enabling the removal and transport of spent fuel canisters from the San Onofre site, as to which there can be no assurance. Cost estimates are subject to change as decommissioning proceeds and such changes may be material.

SCE's share of the San Onofre Units 2 and 3 decommissioning costs recorded during 2023 and 2022 were $226 million (in 2023 dollars) and $187 million (in 2022 dollars), respectively. The CPUC conducts a reasonableness review of recorded decommissioning costs in NDCTPs.

In the 2021 NDCTP, filed in February 2022, SCE requested reasonableness review of approximately $570 million (SCE share in 2022 dollars) of recorded San Onofre Units 2 and 3 decommissioning costs incurred during the period 2018 to

22

Table of Contents

2020. In May 2023, SCE entered into a settlement with the relevant intervenors under which, subject to CPUC approval, SCE agreed to a disallowance in the 2021 NDCTP of approximately $30 million. SCE has accrued for this disallowance.

SCE had nuclear decommissioning trust funds for San Onofre Units 2 and 3 of $2.2 billion at both December 31, 2023 and 2022. Based upon the resolution of a number of uncertainties, including the uncertainties of decommissioning discussed above, the financial performance of the nuclear decommissioning trust fund investments, as well as the resolution of a number of other assumptions and estimates, additional contributions to the nuclear decommissioning trust's funds may be required. If additional contributions to the nuclear decommissioning trust funds become necessary, SCE will seek recovery of additional contributions to the decommissioning trust through electric rates and any such recovery will be subject to a reasonableness review by the CPUC. Cost increases resulting from contractual disputes, delays in performance by the contractor, elevated levels of inflation, or permitting delays, among other things, could cause SCE to materially overrun the decommissioning cost estimate and could materially impact the sufficiency of trust funds.

In December 2023, the CPUC approved disbursements from SCE's nuclear decommissioning trusts to cover forecasted 2024 decommissioning costs for San Onofre Units 2 and 3, of which SCE's share is approximately $300 million in 2024 dollars.

Margin and Collateral Deposits

Certain derivative instruments, power and energy procurement contracts and other contractual arrangements contain collateral requirements. In addition, certain environmental remediation obligations require financial assurance that may be in the form of collateral postings. Future collateral requirements may differ from the requirements at December 31, 2023 due to the addition of incremental power and energy procurement contracts with collateral requirements, if any, the impact of changes in wholesale power and natural gas prices on SCE's contractual obligations, and the impact of SCE's credit ratings falling below investment grade.

The table below provides the amount of collateral posted by SCE to its counterparties as well as the potential collateral that would have been required as of December 31, 2023, if SCE's credit rating had been downgraded to below investment grade as of that date. The table below also provides the potential collateral that could be required due to adverse changes in wholesale power and natural gas prices over the remaining lives of existing power and fuel derivative contracts.

In addition to amounts shown in the table, power and fuel contract counterparties may also institute new collateral requirements, applicable to future transactions to allow SCE to continue trading in power and fuel contracts at the time of a downgrade or upon significant increases in market prices. Furthermore, SCE may also be required to post up to $50 million in collateral in connection with its environmental remediation obligations, within 120 days of the end of the fiscal year in which a downgrade below investment grade occurs.

23

Table of Contents

(in millions)
Collateral posted as of December 31, 20231$217
Incremental collateral requirements for purchased power and fuel contracts resulting from a potential downgrade of SCE's credit rating to below investment grade2102
Incremental collateral requirements for SCE's financial hedging activities resulting from adverse market price movement351
Posted and potential collateral requirements$370

1      Net collateral provided to counterparties and other brokers consisted of $88 million in letters of credit and surety bonds and $129 million of cash collateral.

2      Represents potential collateral requirements for accounts payable and mark-to-market valuation at December 31, 2023. Requirement varies throughout the period and is generally lower at the end of the month.

3      Incremental collateral requirements were based on potential changes in SCE's forward positions as of December 31, 2023 due to adverse market price movements over the remaining lives of the existing power and fuel derivative contracts using a 95% confidence level.

Edison International Parent and Other

In the next 12 months, Edison International expects to fund its net cash requirements through cash on hand, dividends from SCE, and capital market and bank financings. Edison International may finance its ongoing cash requirements, including dividends, working capital requirements, payment of obligations, and capital investments, including capital contributions to subsidiaries, with short-term or other financings, subject to availability in the bank and capital markets.

At December 31, 2023, Edison International Parent had cash on hand of $131 million and $1.3 billion available to borrow on its $1.5 billion revolving credit facility. The credit facility is available for borrowing needs until May 2027.

At December 31, 2023 Edison International Parent had $246 million outstanding commercial paper, net of discount, at a weighted-average interest rate of 5.82% supported by the $1.5 billion revolving credit facility. The aggregate maximum principal amount under the Edison International Parent revolving credit facility may be increased up to $2.0 billion, provided that additional lender commitments are obtained. For further details, see "Notes to Consolidated Financial Statements—Note 5. Debt and Credit Agreements."

Edison International Parent has $500 million of debt maturities arising in the next 12 months. Edison International expects to issue debt to refinance these maturities.

Edison International Parent maintains a program to sell shares of its common stock with aggregate sales price up to $500 million, including through designated broker-dealers at prevailing market prices (an "at-the-market" offering). For further information, see "Notes to Consolidated Financial Statements—Note 14. Equity."

In November 2023, Edison International repurchased 61,497 shares of its Series A Preferred Stock and 84,223 shares of its Series B Preferred Stock through a tender offer. In December 2023, Edison International repurchased 29,186 shares of its Series A Preferred Stock and 133,323 shares of its Series B Preferred Stock on the open market. The aggregate amount paid, including accrued and unpaid dividends, was $133 million for the tender offer repurchase and $155 million for the open market repurchase. Edison International paid the consideration and the fees and expenses incurred with cash on hand and proceeds of debt issuances. For further information, see "Notes to Consolidated Financial Statements—Note 14. Equity."

On February 22, 2024, Edison International declared a dividend of $0.78 per share to be paid on April 30, 2024. Edison International Parent and Other's liquidity and its ability to pay operating expenses and pay dividends to common shareholders are dependent on access to the bank and capital markets, dividends from SCE, realization of tax benefits and its ability to meet California law requirements for the declaration of dividends. Prior to declaring dividends, Edison

24

Table of Contents

International's Board of Directors evaluates available information, including when applicable, information pertaining to the 2017/2018 Wildfire/Mudslide Events, to ensure that the California law requirements for the declarations are met. For information on the California law requirements on the declaration of dividends, see "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—SCE Dividends." Edison International intends to maintain its target payout ratio of 45% – 55% of SCE's core earnings, subject to the factors identified above.

Edison International's ability to declare and pay common dividends may be restricted under the terms of the Series A and Series B Preferred Stock. For further information see "Notes to Consolidated Financial Statements—Note 14. Equity."

Edison International Parent's credit facility requires a consolidated debt to total capitalization ratio as defined in the applicable agreements of less than or equal to 0.70 to 1. At December 31, 2023, Edison International's consolidated debt to total capitalization ratio was 0.63 to 1.

At December 31, 2023, Edison International Parent was in compliance with all financial covenants that affect access to capital.

The following table summarizes Edison International Parent's current long-term issuer credit ratings and outlook from the major credit rating agencies:

Moody'sFitchS&P
Credit RatingBaa2BBBBBB
OutlookStableStableStable

Edison International Parent's credit ratings may be affected if, among other things, regulators fail to successfully implement AB 1054 in a consistent and credit supportive manner, or the Wildfire Insurance Fund is depleted by claims from catastrophic wildfires. Credit rating downgrades increase the cost and may impact the availability of short-term and long-term borrowings, including commercial paper, credit facilities, note financings or other borrowings.

Edison International Income Taxes

Net Operating Loss and Tax Credit Carryforwards

Edison International has approximately $3.4 billion of tax effected net operating losses and tax credit carryforwards at December 31, 2023 (after excluding $106 million of Capistrano Wind attributes and offsetting $363 million of unrecognized tax benefits), which are available to offset future consolidated tax liabilities.

See "Notes to Consolidated Financial Statements—Note 8. Income Taxes" for further information regarding taxes payable to Capistrano Wind.

Inflation Reduction Act of 2022

On August 16, 2022, the IRA was signed into law. The law imposes a 15% corporate alternative minimum tax ("CAMT") on adjusted financial statement income ("AFSI") of corporations with average AFSI exceeding $1.0 billion over a specified 3-year period. The CAMT was effective beginning January 1, 2023. Based on the current interpretation of the law and historical financial data, Edison International estimates that it will exceed the $1.0 billion threshold and be subject to CAMT on its consolidated federal tax returns beginning in 2025. SCE also expects to be subject to CAMT on its stand-alone federal return beginning in 2025.

The law also includes significant extensions, expansions, and enhancements of numerous energy-related investment tax credits, as well as creating new credits applicable to electricity production which may apply to SCE's capital expenditures. Under the IRA, SCE expects to generate investment tax credits related to its utility owned storage projects, which will accrue to the benefit of its customers.

25

Table of Contents

Historical Cash Flows

SCE

Years ended December 31,
(in millions)202320222021
Net cash provided by operating activities$3,681$3,319$158
Net cash provided by financing activities1,1822,7245,218
Net cash used in investing activities(5,231)(5,557)(5,152)
Net (decrease) increase in cash, cash equivalents and restricted cash$(368)$486$224

Net Cash Provided by Operating Activities

The following table summarizes major categories of net cash provided by operating activities as provided in more detail in SCE's consolidated statements of cash flows for 2023, 2022 and 2021:

Years ended December 31,Change
(in millions)2023202220212023/2022
Net income$1,597954$935
Non-cash items12,9792,7012,534
Subtotal4,5763,6553,469$921
Contributions to Wildfire Insurance Fund(95)(95)(95)
Changes in cash flow resulting from working capital2(762)327(705)(1,089)
Regulatory assets and liabilities576(51)(720)627
Wildfire related claims3(410)(56)(2,648)(354)
Proceeds from Morongo Transmission LLC400
Other noncurrent assets and liabilities4(204)(461)457257
Net cash provided by operating activities$3,681$3,319$158$362
Column 1Column 2
1Non-cash items include depreciation and amortization, allowance for equity during construction, impairment and other income, Wildfire Insurance Fund amortization expense, deferred income taxes and other.
Column 1Column 2
2Changes in working capital items include receivables, unbilled revenue, inventory, amortization of prepaid expenses, accounts payable, tax receivables and payables, derivative assets and liabilities and other current assets and liabilities.
Column 1Column 2
3The amount in 2023 represents payments of $1.0 billion for 2017/2018 Wildfire/Mudslide Events and $190 million for Post-2018 Wildfires, partially offset by an increase in wildfire estimated losses of $814 million. The 2022 amount includes payments of $1.9 billion settlements on 2017/2018 Wildfire/Mudslide Events claims, partially offset by an increase of estimated losses of $1.3 billion on 2017/2018 Wildfire/Mudslide Events and $0.6 billion on Post-2018 Wildfires.
Column 1Column 2
4Includes nuclear decommissioning trusts. See “Nuclear Decommissioning Activities” below for further information. Also includes changes in wildfire-related insurance receivables.

Net cash provided by operating activities was impacted by the following:

Net income and non-cash items increased in 2023 by $921 million from 2022 primarily due to higher revenue due to the escalation mechanism as set forth in the 2021 GRC final decision and higher interest income on balancing account undercollections and lower wildfire estimated losses, partially offset by higher interest expense.

Net cash (outflow) inflow for working capital was $(762) million and $327 million in 2023 and 2022, respectively. The net cash outflow for working capital for 2023 was primarily due to decrease in payables of $402 million driven by payments on power purchase contracts and a decrease in gas price from December 2022, and increases in customer receivables and unbilled revenue of approximately $300 million due to various customer protection programs in place. The net cash inflow for working capital for 2022 was mainly due to an increase in payables of $343 million driven by

26

Table of Contents

higher payables on power purchase contracts and a net decrease of $24 million in customer receivables and unbilled revenue primarily from $387 million of CAPP funds received in 2022, partially offset by lower collections.

Net cash used in regulatory assets and liabilities, including the increase in net undercollections of balancing and memorandum accounts, was affected by differences between timing of collection of amounts through rates and accrual expenditures. Cash inflows of $576 million in 2023 were primarily due to recovery of prior year undercollections, partially offset by current year undercollections due to lower sales volume driven by mild weather. Cash outflows of $51 million in 2022 were primarily due to increased undercollections driven by higher energy prices and power purchase load, partially offset by recovery of prior year undercollections and current year higher sales volume and average rates driven by extreme heat in California.

Net Cash Provided by Financing Activities

The following table summarizes cash provided by financing activities for 2023, 2022 and 2021. Issuances of debt is discussed in "Notes to Consolidated Financial Statements—Note 5. Debt and Credit Agreements."

Years ended December 31,
(in millions)202320222021
Issuances of long-term debt, including premium/discount and net of issuance costs$3,588$5,032$5,411
Long-term debt repaid or repurchased(2,098)(385)(1,037)
Short-term debt borrowed7062,654
Short-term debt repaid(1,051)(1,543)(2,255)
Commercial paper borrowing (repayments), net963(406)(124)
Preference stock issued, net of issuance cost542
Capital contributions from Edison International Parent1,4001,633
Payment of common stock dividends to Edison International Parent(1,400)(1,300)(975)
Payment of preference stock dividends(117)(110)(106)
Other493617
Net cash provided by financing activities$1,182$2,724$5,218

Net Cash Used in Investing Activities

Cash flows used in investing activities are primarily due to capital expenditures and funding of nuclear decommissioning trusts. Cash used in capital expenditures were $5.4 billion, $5.8 billion and $5.5 billion for 2023, 2022 and 2021, respectively, primarily related to transmission, distribution and generation investments. SCE had a net redemption of nuclear decommissioning trust investments of $180 million, $123 million and $256 million in 2023, 2022 and 2021, respectively. See "Nuclear Decommissioning Activities" below for further discussion.

27

Table of Contents

Nuclear Decommissioning Activities

SCE's statements of cash flows include nuclear decommissioning activities, which are reflected in the following line items:

Years ended December 31,
(in millions)202320222021
Net cash used in operating activities:
Net earnings (losses) from nuclear decommissioning trust investments$42$78$(31)
SCE's decommissioning costs(229)(189)(238)
Net cash provided by investing activities:
Proceeds from sale of investments4,5974,1773,961
Purchases of investments(4,417)(4,054)(3,705)
Net cash (outflow) inflow$(7)$12$(13)

Net cash used in operating activities relates to interest and dividends less administrative expenses, taxes and SCE's decommissioning costs. Investing activities represent the purchase and sale of investments within the nuclear decommissioning trusts, including the reinvestment of earnings from nuclear decommissioning trust investments.

Funds for decommissioning costs are requested from the nuclear decommissioning trusts one month in advance. Decommissioning disbursements are funded from sales of investments of the nuclear decommissioning trusts. The net cash impact reflects timing of decommissioning payments ($229 million, $189 million and $238 million in 2023, 2022 and 2021, respectively) and reimbursements to SCE from the nuclear decommissioning trust ($222 million, $201 million and $225 million in 2023, 2022 and 2021, respectively).

Edison International Parent and Other

The table below sets forth condensed historical cash flow from operations for Edison International Parent and Other, including intercompany eliminations.

Years ended December 31,
(in millions)202320222021
Net cash used in operating activities$(280)$(103)$(147)
Net cash provided by financing activities265157227
Net cash (used in) provided by investing activities(2)(17)1
Net (decrease) increase in cash, cash equivalents and restricted cash$(17)$37$81

Net Cash Used in Operating Activities

Net cash used in operating activities increased in 2023 by $177 million from 2022 due to:

Column 1Column 2
Outflows of $280 million and $193 million from operating activities in 2023 and 2022, respectively, due to payments relating to interest and operating costs.
Column 1Column 2
$90 million cash inflow from a wildfire insurance premium received by EIS in 2022.

28

Table of Contents

Net Cash Provided by Financing Activities

Net cash provided by financing activities was as follows:

Years ended December 31,
(in millions)202320222021
Dividends paid to Edison International common shareholders$(1,112)$(1,050)$(988)
Dividends paid to Edison International preferred shareholders(108)(99)(35)
Dividends received from SCE1,4001,300975
Capital contributions to SCE(1,400)(1,633)
Issuance of common stock201332
Issuance of preferred stock, net of issuance costs1,977
Long-term debt issuance, net of discount and issuance costs1,533939
Long-term debt repayments(400)(700)
Issuance of short-term debt3701,000
Repayments of short-term debt(1,356)
Preferred stock repurchased(289)
Commercial paper financing, net13989(130)
Other686529
Net cash provided by financing activities$265$157$227

Net Cash (Used in) Provided by Investing Activities

Net cash used in investing activities in 2022 included a net cash outflow of $17 million for a business acquisition at Edison Energy.

Contractual Obligations and Contingencies

Contractual Obligations

SCE and Edison International Parent and Other have various contractual obligations, which are recorded as liabilities in the consolidated financial statements. Other items, such as certain purchase commitments and other executory contracts, are not recognized as liabilities in the consolidated financial statements but are required to be disclosed in the footnotes to the financial statements.

For details on long-term debt, see "Notes to Consolidated Financial Statements—Note 5. Debt and Credit Agreements."

Certain power purchase agreements which SCE entered into with independent power producers are treated as operating or finance leases. In addition, SCE has other operating lease obligations primarily related to vehicles, office space and other equipment. For further discussion, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies" and "—Note 13. Leases."

SCE also has other purchase obligations primarily related to maintaining reliability and expanding SCE's transmission and distribution system and nuclear fuel supply contracts. For further discussion, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies."

Edison International Parent and Other and SCE have estimated contributions to the pension and PBOP plans. These amounts represent estimates that are based on assumptions that are subject to change. See "Notes to Consolidated Financial Statements—Note 9. Compensation and Benefit Plans" for further information.

Edison International and SCE have a total net liability recorded for uncertain tax positions. Edison International and SCE cannot make reliable estimates of the cash flows by period due to uncertainty surrounding the timing of resolving these

29

Table of Contents

open tax issues with the tax authorities. See "Notes to Consolidated Financial Statements—Note 8. Income Taxes" for further information.

For details on derivative obligations and asset retirement obligations, see "Notes to Consolidated Financial Statements—Note 6. Derivative Instruments" and "—Note 1. Summary of Significant Accounting Policies," respectively.

Contingencies

Edison International's and SCE's contingencies are discussed in "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies."

Off-Balance Sheet Arrangements

SCE has variable interests in power purchase contracts with variable interest entities and a variable interest in unconsolidated Trust II, Trust III, Trust IV, Trust V, Trust VI and Trust VII that issued $220 million of 5.10%, $275 million of 5.75%, $325 million of 5.375%, $300 million of 5.45%, $475 million of 5.00% and $550 million of 7.50% trust securities, respectively, to the public. All dollar amounts shown are the aggregate liquidation preference. See "Notes to Consolidated Financial Statements—Note 3. Variable Interest Entities."

MARKET RISK EXPOSURES

Edison International's and SCE's primary market risks include fluctuations in interest rates, commodity prices and volumes, and counterparty credit. Derivative instruments are used to manage market risks including market risks to SCE's customers. For further discussion of market risk exposures, including commodity price risk, credit risk and interest rate risk, see "Notes to Consolidated Financial Statements—Note 6. Derivative Instruments" and "—Note 4. Fair Value Measurements."

Interest Rate Risk

Edison International and SCE are exposed to changes in interest rates primarily as a result of financing, investing and borrowing activities used for liquidity purposes, and to fund business operations and capital investments. The nature and amount of Edison International's and SCE's long-term and short-term debt can be expected to vary as a result of future business requirements, market conditions and other factors. Fluctuations in interest rates can affect earnings and cash flows. Changes in interest rates may impact SCE's authorized rate of return for the period beyond 2024 through a CPUC cost of capital adjustment mechanism, see "Management Overview—Cost of Capital Trigger" and "Business—SCE—Overview of Ratemaking Process" for further discussion. The following table summarizes the increase or decrease to the fair value of long-term debt including the current portion, if the market interest rates were changed while leaving all other assumptions the same:

(in millions)Carrying ValueFair Value10% Increase10% Decrease
Edison International:
December 31, 2023$33,013$31,315$30,060$32,684
December 31, 202229,63926,82425,73928,006
SCE:
December 31, 202328,49426,71225,59327,930
December 31, 202226,25823,46922,44424,590

Commodity Price Risk

SCE and its customers are exposed to the risk of a change in the market price of natural gas, electric power and transmission congestion. Due to regulatory mechanisms, exposure to commodity prices is not expected to impact earnings but may impact timing of cash flows. SCE's hedging program is designed to reduce exposure to variability in market prices related to SCE's purchases and sales of electric power and natural gas. As part of this program, SCE enters

30

Table of Contents

into energy options, swaps, forward arrangements and congestion revenue rights ("CRRs"). The transactions are pre-approved by the CPUC or executed in compliance with CPUC-approved procurement plans. Therefore, SCE expects recovery of its related hedging costs, as well as procurement costs, through the ERRA balancing account or CPUC-approved procurement plans. For more details of the ERRA balancing account, see "Business—SCE—Overview of Ratemaking Process."

Fair Value of Derivative Instruments

The fair value of derivative instruments is included in the consolidated balance sheets unless subject to an exception under the applicable accounting guidance. Realized gains and losses from derivative instruments are expected to be recovered from or refunded to customers through regulatory mechanisms and, accordingly, changes in the fair value of derivative instruments have no impact on earnings. SCE does not use hedge accounting for these transactions due to this regulatory accounting treatment. For further discussion on fair value measurements and the fair value hierarchy, see "Notes to Consolidated Financial Statements—Note 4. Fair Value Measurements."

The fair value of outstanding derivative instruments used to mitigate exposure to commodity price risk was a net asset of $91 million and $240 million at December 31, 2023 and 2022, respectively.

The following table summarizes the increase or decrease to the fair values of the net asset of derivative instruments included in the consolidated balance sheets, if the electricity prices or gas prices were changed while leaving all other assumptions constant:

December 31,
(in millions)20232022
Increase in electricity prices by 10%$26$22
Decrease in electricity prices by 10%(26)(22)
Increase in gas prices by 10%540
Decrease in gas prices by 10%(5)(40)

Investment Price Risk

Edison International and SCE are subject to investment price risk due to securities held as investments in the nuclear decommissioning trust and various pension and other post-retirement benefit plan trusts.

Nuclear Decommissioning Trust

As of December 31, 2023, SCE's nuclear decommissioning trust investments include equity investments of $1.7 billion and fixed income investments of $2.3 billion. These investments are exposed to price fluctuations in equity markets and changes in interest rates. SCE's investment policies and CPUC requirements place limitations on the types and investment grade ratings of the securities that may be held by the nuclear decommissioning trust. These policies restrict the trust from holding alternative investments and limit the trust funds' exposures to investments in highly illiquid markets. Due to regulatory mechanisms, investment earnings and realized and unrealized gains and losses increase or decrease the trust assets and the related regulatory asset or liability, and do not materially affect earnings. For further discussion on the nuclear decommissioning trust investments, see "Notes to Consolidated Financial Statements—Note 4. Fair Value Measurements" and "—Note 10. Investments."

PBOP and Pension Plan Assets

The PBOP Plan and the Southern California Edison Company Retirement Plan Trust assets include investments in equity securities, U.S. treasury securities, other fixed-income securities, common/collective funds, mutual funds, other investment entities, foreign exchange and interest rate contracts, and partnership/joint ventures. These investments are exposed to price fluctuations in equity markets and changes in interest rates. The investment of plan assets is overseen by a fiduciary investment committee. Risk is managed through diversification among multiple asset classes, managers,

31

Table of Contents

styles and securities. See "Notes to Consolidated Financial Statements—Note 9. Compensation and Benefit Plans" for additional information regarding investment strategy of plan assets.

Contributions related to SCE employees made to SCE pension plan are anticipated to be recovered through CPUC-approved regulatory mechanisms.

Credit Risk

Credit risk exposure from counterparties for power and gas trading activities is measured as the sum of net accounts receivable (accounts receivable less accounts payable) and the current fair value of net derivative assets (derivative assets less derivative liabilities) reflected on the consolidated balance sheets. SCE enters into master agreements which typically provide for a right of set-off. Accordingly, SCE's credit risk exposure from counterparties is based on a net exposure under these arrangements. SCE manages the credit risk on the portfolio of counterparties based on credit ratings and other publicly disclosed information, such as financial statements, regulatory filings and press releases, to guide it in the process of setting credit levels, risk limits and contractual arrangements, including master netting agreements. Based on SCE's policies and risk exposures related to credit, SCE does not anticipate a material adverse effect on their financial statements as a result of counterparty nonperformance. At December 31, 2023, SCE's power and gas trading counterparty credit risk exposure was $91 million, all of which is associated with entities that have an investment grade rating of A or higher. SCE assigns a credit rating to counterparties based on the lowest of a counterparty's S&P's, Moody's and Fitch's rating.

For more information related to credit risks, see "Notes to Consolidated Financial Statements—Note 6. Derivative Instruments."

CRITICAL ACCOUNTING ESTIMATES AND POLICIES

The accounting policies described below are considered critical to obtaining an understanding of Edison International's and SCE's consolidated financial statements because their application requires the use of significant estimates and judgments by management in preparing the consolidated financial statements. Management estimates and judgments are inherently uncertain and may differ significantly from actual results achieved. Management considers an accounting estimate to be critical if the estimate requires significant assumptions and changes in the estimate or, the use of alternative estimates, could have a material impact on Edison International's and SCE's results of operations or financial position. For more information on Edison International's and SCE's accounting policies, see "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies."

Accounting for Contingencies

Nature of Estimates Required. Edison International and SCE record loss contingencies when management determines that the outcome of future events is probable of occurring and when the amount of the loss can be reasonably estimated. Gain contingencies are recognized in the financial statements when they are realized.

Key Assumptions and Approach Used. The determination of an accrual for a loss contingency is based on management judgment and estimates with respect to the likely outcome of the matter, including the analysis of different scenarios. Liabilities are recorded or adjusted when events or circumstances cause these judgments or estimates to change. In assessing whether a loss is a reasonable possibility, Edison International and SCE may consider the following factors, among others: the nature of the litigation, claim or assessment, opinions or views of legal counsel and other advisors, and the experience gained from similar cases. Edison International and SCE provide disclosures for material contingencies when there is a reasonable possibility that a loss or an additional loss may be incurred.

Effect if Different Assumptions Used. Actual amounts realized upon settlement of contingencies may be different than amounts recorded and disclosed and could have a significant impact on the liabilities, revenue and expenses recorded on

32

Table of Contents

the consolidated financial statements. For a discussion of contingencies, guarantees and indemnities, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies."

Application to Wildfires

As discussed in "Management Overview," wildfires in SCE's territory have caused loss of life, substantial damage to both residential and business properties, and service outages for SCE customers.

The extent of legal liability for wildfire-related damages in actions against utilities depends on a number of factors, including whether the utility substantially caused or contributed to the damages and whether parties seeking recovery of damages will be required to show negligence in addition to causation. Final determinations of legal liability for wildfire events, including determinations of whether SCE was negligent, would only be made during lengthy and complex litigation processes and settlements may be reached before determinations of legal liability are ever made.

Edison International and SCE have incurred material losses in connection with several wildfires. Estimated losses for wildfire litigation are based on a number of assumptions and are subject to change as additional information becomes available. Actual losses incurred may be higher or lower than estimated based on several factors, including the uncertainty in estimating damages that have been or may be alleged. For instance, SCE will receive additional information with respect to damages claimed as the claims mediation and trial processes progress. Other factors that can cause actual losses incurred to be higher or lower than estimated include the ability to reach settlements and the outcomes of settlements reached through the ongoing claims mediation and trial processes, uncertainties related to the sufficiency of insurance held by plaintiffs, uncertainties related to the litigation processes, including whether plaintiffs will ultimately pursue claims, uncertainty as to the legal and factual determinations to be made during litigation, including uncertainty as to the contributing causes of certain wildfires, and the uncertainty as to how these factors impact future settlements.

For more information related to the loss contingencies of the wildfires, see "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides."

Rate Regulated Enterprises

Nature of Estimate Required.   SCE follows the accounting principles for rate-regulated enterprises which are required for entities whose rates are set by regulators at levels intended to recover the estimated costs of providing service, plus a return on net investment, or rate base. Regulators may also impose penalties or grant incentives. Due to timing and other differences in the collection of revenue, these accounting principles allow a cost that would otherwise be charged as an expense by an unregulated entity to be capitalized as a regulatory asset if it is probable that such cost is recoverable through future rates; conversely the accounting principles require creation of a regulatory liability for amounts collected in rates to recover costs expected to be incurred in the future or amounts collected in excess of costs incurred and refundable to customers. In addition, SCE recognizes revenue and regulatory assets from alternative revenue programs, which enables the utility to adjust future rates in response to past activities or completed events, if certain criteria are met, even for programs that do not qualify for recognition of "traditional" regulatory assets and liabilities.

Accounting principles for rate-regulated enterprises also require recognition of an impairment loss if it becomes probable that the regulated utility will abandon a plant investment, or if it becomes probable that the cost of a recently completed plant will be disallowed, either directly or indirectly, for ratemaking purposes and a reasonable estimate of the amount of the disallowance can be made.

Key Assumptions and Approach Used.   SCE's management assesses at the end of each reporting period whether regulatory assets are probable of future recovery by considering factors such as the current regulatory environment, the issuance of rate orders on recovery of the specific or a similar incurred cost to SCE or other rate-regulated entities, and

33

Table of Contents

other factors that would indicate that the regulator will treat an incurred cost as allowable for ratemaking purposes. Using these factors, management has determined that existing regulatory assets and liabilities are probable of future recovery or settlement. This determination reflects the current regulatory climate and is subject to change in the future. SCE also considers whether any plant investments are probable of abandonment or disallowance.

Effect if Different Assumptions Used.   Significant management judgment is required to evaluate the anticipated recovery of regulatory assets and plant investments, the recognition of incentives and revenue subject to refund, as well as the anticipated cost of regulatory liabilities or penalties. If future recovery of costs ceases to be probable, all or part of the regulatory assets, plant investments and/or liabilities would have to be written off against current period earnings. At December 31, 2023, the consolidated balance sheets included regulatory assets of $11.4 billion and regulatory liabilities of $10.2 billion. If different judgments were reached on recovery of costs and timing of income recognition, SCE's earnings may vary from the amounts reported.

Application to Southern California Wildfires

Application to 2017/2018 Wildfire/Mudslide Events

Recovery of SCE's losses realized in connection with the 2017/2018 Wildfire/Mudslide Events in excess of available insurance is subject to approval by regulators. Under accounting standards for rate-regulated enterprises, SCE defers costs as regulatory assets when it concludes that such costs are probable of future recovery in electric rates. SCE utilizes objectively determinable evidence to form its view on probability of future recovery. The only directly comparable precedent in which a California investor-owned utility has sought recovery for uninsured wildfire claims related costs is SDG&E's requests for cost recovery related to 2007 wildfire activity, where the FERC allowed recovery of all FERC-jurisdictional wildfire claims related costs while the CPUC rejected recovery of all CPUC-jurisdictional wildfire claims related costs based on a determination that SDG&E did not meet the CPUC's prudency standard. As a result, while SCE does not agree with the CPUC's decision, it believes that the CPUC's interpretation and application of the prudency standard to SDG&E creates substantial uncertainty regarding how that standard will be applied to an investor-owned utility in cost-recovery proceedings for wildfire claims related to fires ignited prior to July 12, 2019. SCE will continue to evaluate the probability of recovery based on available evidence, including judicial, legislative and regulatory decisions, including any CPUC decisions illustrating the interpretation and/or application of the prudency standard when making determinations regarding recovery of uninsured wildfire-related costs. While the CPUC has not made a determination regarding SCE's prudency relative to any of the 2017/2018 Wildfire/Mudslide Events, SCE is unable to conclude, at this time, that uninsured CPUC-jurisdictional wildfire-related costs for these events are probable of recovery through electric rates. SCE would record a regulatory asset at the time it obtains sufficient information to support a conclusion that recovery is probable.

Through the operation of its FERC Formula Rate, and based upon the precedent established in SDG&E's recovery of FERC-jurisdictional wildfire-related costs, SCE believes it is probable it will recover its FERC-jurisdictional wildfire and mudslide related costs and has recorded total expected recoveries within the FERC balancing account.

Application to Post-2018 Wildfires

Management judgment is required to assess the probability of recovery of SCE's losses realized in connection with the Post-2018 Wildfires in excess of available insurance.

The CPUC and FERC may not allow SCE to recover uninsured losses through electric rates if it is determined that such losses were not reasonably or prudently incurred. On July 12, 2019, AB 1054 clarified that the CPUC must allow recovery of costs and expenses arising from a covered wildfire if the utility's conduct related to the ignition was consistent with actions that a reasonable utility would have undertaken in good faith under similar circumstances, at the relevant point in time, and based on the information available at that time. Further, utilities with a valid safety

34

Table of Contents

certification at the time of the relevant wildfire will be presumed to have acted prudently related to a wildfire ignition unless a party in the cost recovery proceeding creates "serious doubt" as to the reasonableness of the utility's conduct, at which time, the burden shifts back to the utility to dispel that doubt and prove its conduct was prudent. The serious doubt standard in AB 1054 is modeled after the FERC cost recovery standard. SCE evaluates the probability of recovery of costs related to the Post-2018 Wildfires in the context of the prudency standard laid out by AB 1054 above, including how the FERC applies the serious doubt standard. SCE’s evaluation also relies on its status as a holder of a valid safety certificate, facts and other evidence known to date related to the ignition, and any regulatory decisions illustrating the interpretation and/or application of the prudency standard under AB 1054, which as of December 31, 2023, has not been applied by the CPUC to an actual cost recovery application filed by any California investor-owned utility. SCE also considers which costs are eligible for recovery based on precedent from other CPUC cost recovery proceedings. Management's assessment of the probability of recovery may change, related to changes in any of these factors in the future.

See "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides—Post-2018 Wildfires" for further discussion of regulatory assets recorded for Post-2018 Wildfires as of December 31, 2023.

Income Taxes

Nature of Estimates Required.   As part of the process of preparing its consolidated financial statements, Edison International and SCE are required to estimate income taxes for each jurisdiction in which they operate. This process involves estimating actual current period tax expense together with assessing temporary differences resulting from differing treatment of items, such as depreciation, for tax and accounting purposes. These differences result in deferred tax assets and liabilities, which are included within Edison International's and SCE's consolidated balance sheets, including net operating loss and tax credit carryforwards. Certain estimates and assumptions are required to determine whether deferred tax assets can and will be utilized in future periods. Based on currently enacted tax laws, Edison International expects to generate sufficient taxable income to fully utilize all loss and credit carryovers set to expire beyond 2023.

Edison International and SCE take certain tax positions they believe are in accordance with the applicable tax laws. However, these tax positions are subject to interpretation by the Internal Revenue Service, state tax authorities and the courts. Edison International and SCE determine uncertain tax positions in accordance with the authoritative guidance.

Key Assumptions and Approach Used.   In determining whether it is more likely than not that all or some portion of net operating loss and tax credit carryforwards can be utilized, management analyzes the trend of GAAP earnings and then estimates the impact of future taxable income, reversing temporary differences and available prudent and feasible tax planning strategies based on currently enacted tax laws.

Accounting for tax obligations requires management judgment. Edison International's and SCE's management use judgment in determining whether the evidence indicates it is more likely than not, based solely on the technical merits, that a tax position will be sustained, and to determine the amount of tax benefits to be recognized. Judgment is also used in determining the likelihood a tax position will be settled and possible settlement outcomes. In assessing uncertain tax positions Edison International and SCE consider, among others, the following factors: the facts and circumstances of the position, regulations, rulings, and case law, opinions or views of legal counsel and other advisers, and the experience gained from similar tax positions. Edison International and SCE evaluate uncertain tax positions at the end of each reporting period and make adjustments when warranted based on changes in fact or law.

Effect if Different Assumptions Used.   Should a change in facts or circumstances, including a change in enacted tax legislation, lead to a change in judgment about the ultimate realizability of a deferred tax asset, Edison International and

35

Table of Contents

SCE would record or adjust the related valuation allowance in the period that the change in facts and circumstances occurs, along with a corresponding increase or decrease in the provision for income taxes.

Actual income taxes may differ from the estimated amounts which could have a significant impact on the liabilities, revenue and expenses recorded in the financial statements. Edison International and SCE continue to be under audit or subject to audit for multiple years in various jurisdictions. Significant judgment is required to determine the tax treatment of particular tax positions that involve interpretations of complex tax laws. Such liabilities are based on judgment and a final determination could take many years from the time the liability is recorded. Furthermore, settlement of tax positions included in open tax years may be resolved by compromises of tax positions based on current factors and business considerations that may result in material adjustments to income taxes previously estimated. For a discussion of current and deferred taxes, net operating losses and tax credit carryforwards, accounting for uncertainty in income taxes, unrecognized tax benefits, and tax disputes, see "Notes to Consolidated Financial Statements—Note 8. Income Taxes."

Nuclear Decommissioning – Asset Retirement Obligation

Key Assumptions and Approach Used.   San Onofre Units 1, 2 and 3 decommissioning cost estimates are updated in each NDCTP and when there are material changes to the timing or amount of estimated future cash flows. Palo Verde decommissioning cost estimates are updated by the operating agent, Arizona Public Services, every three years and when there are material changes to the timing or amount of estimated future cash flows. SCE estimates that it will spend approximately $6.1 billion, undiscounted through 2080, to decommission its nuclear facilities.

The current ARO estimates for San Onofre and Palo Verde are based on:

Column 1Column 2
Decommissioning Costs. The estimated costs for labor, material, equipment and other, and low-level radioactive waste costs are included in each of the NRC decommissioning stages: license termination, site restoration and spent fuel storage. The liability to decommission SCE's nuclear power facilities is based on a 2020 decommissioning study, filed as part of the 2021 NDCTP, for San Onofre Unit 1, 2 and 3 and a 2019 decommissioning study for Palo Verde, with revisions to the cost estimate in 2020.
Column 1Column 2
Escalation Rates. Annual escalation rates are used to convert the decommissioning cost estimates in base year dollars to decommissioning cost estimates in future-year dollars. Escalation rates are primarily used for labor, material, equipment and low-level radioactive waste burial costs. SCE's current estimates are based upon SCE's decommissioning cost methodology used for ratemaking purposes. Average escalation rates range from 2.2% to 7.5% (depending on the cost element) annually.
Column 1Column 2
Timing. Initial decommissioning activities at San Onofre Unit 1 started in 1999 and at Units 2 and 3 in 2013. Cost estimates for San Onofre Units are currently based on completion of decommissioning activities by 2053. Cost estimates for Palo Verde are based on an assumption that decommissioning will commence promptly after the current NRC operating licenses expire. The Palo Verde 1, 2, 3 operating licenses currently expire in 2045, 2046 and 2047, respectively.
Column 1Column 2
Spent Fuel Dry Storage Costs. Cost estimates, including the impact of escalations, are based on an assumption that the U.S. Department of Energy will begin to take spent fuel from the nuclear industry in 2031 and will remove the last spent fuel from the San Onofre and Palo Verde sites by 2051 and 2078, respectively.
Column 1Column 2
Changes in Decommissioning Technology, Regulation and Economics. The current cost studies assume the use of current technologies under current regulations and at current cost levels.

See "Liquidity and Capital Resources—SCE—Decommissioning of San Onofre" for further discussion of the plans for decommissioning of San Onofre.

36

Table of Contents

Effect if Different Assumptions Used.   The ARO for decommissioning SCE's nuclear facilities was $2.2 billion as of December 31, 2023, based on the most recent decommissioning studies performed and the subsequent cost estimate updates. Changes in the estimated costs, execution strategy or timing of decommissioning, or in the assumptions and judgments by management underlying these estimates, could cause material revisions to the estimated total cost to decommission these facilities which could have a material effect on the recorded liability.

The following table illustrates the increase to the ARO liability if the cost escalation rate was adjusted while leaving all other assumptions constant:

Increase to ARO at
(in millions)December 31, 2023
Uniform increase in escalation rate of 1 percentage point$587

The increase in the ARO liability driven by an increase in the escalation rate would result in a decrease in the regulatory liability for recoveries in excess of ARO liabilities.

Pensions and Postretirement Benefits Other than Pensions

Nature of Estimate Required.   Authoritative accounting guidance requires companies to recognize the overfunded or underfunded status of defined benefit pension and other postretirement plans as assets and liabilities in the balance sheet; the assets and/or liabilities are normally offset through other comprehensive income (loss). In accordance with authoritative guidance for rate-regulated enterprises, regulatory assets and liabilities are recorded instead of charges and credits to other comprehensive income (loss) for its postretirement benefit plans that are recoverable in utility rates. Edison International and SCE have a fiscal year-end measurement date for all of their postretirement plans.

Key Assumptions of Approach Used.   Pension and other postretirement benefit obligations and the related effects on results of operations are calculated using actuarial models. Two critical assumptions, discount rate and expected return on assets, are important elements of plan expense, and the discount rate is important to liability measurement. Other assumptions, which require management judgment, include the rate of compensation increases and rates of retirement and turnover. Additionally, health care cost trend rates are critical assumptions for postretirement health care plans. These critical assumptions are evaluated periodically and updated to reflect actual experience, as appropriate.

As of December 31, 2023, Edison International's and SCE's pension plans had a $3.6 billion and $­­3.3 billion projected benefit obligation, respectively, and total 2023 expense for these plans was $23 million and $18 million, respectively. As of December 31, 2023, the accumulated benefit obligation for Edison International's and SCE's PBOP plans were $773 million and $769 million, respectively, and there were no expenses for Edison International's and SCE's PBOP plans for 2023. The majority of annual contributions made to SCE's pension and PBOP plan are anticipated to be recovered through CPUC-approved regulatory mechanisms and are expected to be, at a minimum, equal to the related annual expense.

Pension expense is recorded for SCE based on the amount funded to the trusts, as calculated using an actuarial method required for ratemaking purposes, in which the impact of market volatility on plan assets is recognized in earnings on a more gradual basis. Any difference between pension expense calculated in accordance with ratemaking methods and pension expense calculated in accordance with authoritative accounting guidance for pension is accumulated as a regulatory asset or liability, and is expected, over time, to be recovered from or returned to customers. As of December 31, 2023, this cumulative difference amounted to $110 million, meaning that the ratemaking method has recognized less in expense than the accounting method since implementation of authoritative guidance for employers' accounting for pensions in 1987, which was offset by a regulatory liability for the current funding level of SCE's pension plan.

37

Table of Contents

Edison International and SCE used the following critical assumptions to determine expense for pension and PBOP for 2023:

PensionPBOP
(in millions)PlansPlans
Discount rate15.36%5.43%
Expected long-term return on plan assets26.50%5.00%
Assumed health care cost trend rates3*6.75%

*     Not applicable to pension plans.

Column 1Column 2
1The discount rate enables Edison International and SCE to state expected future cash flows at a present value on the measurement date. Edison International and SCE select its discount rate by performing a yield curve analysis. This analysis determines the equivalent discount rate on projected cash flows by matching the timing and amount of expected future benefit payments to the corresponding yields from the Willis Towers Watson RATE: Link 10th – 90th percentile yield curve model on the measurement date.
Column 1Column 2
2To determine the expected long-term rate of return on pension plan assets, current and expected asset allocations are considered, as well as historical and expected returns on plan assets. A portion of PBOP trusts asset returns are subject to taxation, so the 5% rate of return on plan assets above is determined on an after-tax basis. Actual time-weighted, annualized returns on the pension plan assets were 11.1%, 7.8% and 6.9% for the one-year, five-year and ten-year periods ended December 31, 2023, respectively. Actual time-weighted, annualized returns on the PBOP plan assets were 8.0%, 4.7% and 4.8% over these same periods. Accounting principles provide that differences between expected and actual returns are recognized over the average future service of employees.
Column 1Column 2
3The health care cost trend rate gradually declines to 5% for 2029 and beyond.

As of December 31, 2023, Edison International and SCE had unrecognized net pension gains of $138 million and $151 million, respectively, and unrecognized PBOP gains of $1.5 billion. The unrecognized pension and PBOP gains primarily consisted of the cumulative impact of the increased discount rates on the respective benefit obligations and the cumulative difference between the expected and actual rate of return on plan assets. Of these deferred gains, $159 million of SCE's pension gains and $1.5 billion of SCE's PBOP gains are recorded as regulatory liabilities, respectively, and are expected to be amortized to expense over the expected future service of the employees (subject to regulatory adjustment) or refunded to ratepayers at the termination or completion of the plan.

Edison International's and SCE's pension and PBOP plans are subject to limits established for federal tax deductibility. SCE funds its pension and PBOP plans in accordance with amounts allowed by the CPUC. Executive pension plans have no plan assets.

Effect if Different Assumptions Used.   Changes in the estimated costs or timing of pension and other postretirement benefit obligations, or the assumptions and judgments used by management underlying these estimates, could have a material effect on the recorded expenses and liabilities.

The following table summarizes the increase or decrease to projected benefit obligation for pension and the accumulated benefit obligation for PBOP if the discount rate were changed while leaving all other assumptions constant:

​ The following table summarizes the increase or decrease to projected benefit obligation for pension and the accumulated benefit obligation for PBOP if the discount rate were changed while leaving all other assumptions constant: ​
Edison InternationalSCE
Increase inDecrease inIncrease inDecrease in
discount ratediscount ratediscount ratediscount rate
(in millions)by 1%by 1%by 1%by 1%
Change to projected benefit obligation for pension$(136)$158$(111)$129
Change to accumulated benefit obligation for PBOP(77)92(76)92

38

Table of Contents

A one percentage point increase in the expected rate of return on pension plan assets would decrease Edison International's and SCE's current year expense by $35 million and $33 million, respectively, and a one percentage point increase in the expected rate of return on PBOP plan assets would decrease both Edison International's and SCE's current year expense by $23 million.

Contributions to the Wildfire Insurance Fund

Nature of Estimates Required. At December 31, 2023, Edison International and SCE have a $2.0 billion long-term asset and a $204 million current asset reflected as "Wildfire Insurance Fund contributions" in the consolidated balance sheets for the initial $2.4 billion contribution made during 2019 and the present value of annual contributions SCE committed to make to the Wildfire Insurance Fund, reduced by amortization. At December 31, 2023, a long-term liability of $450 million has been reflected in "Other deferred credits and other long-term liabilities" for the present value of unpaid contribution amounts. Contributions were discounted to the present value at the date SCE committed to participate in the Wildfire Insurance Fund using US treasury interest rates.

Management concluded it would be most appropriate to account for the contributions to the Wildfire Insurance Fund similar to prepaid insurance, ratably allocating the expense to periods based on an estimated period of coverage.

Key Assumptions and Approach Used. The Wildfire Insurance Fund does not have a defined life. Instead, the Wildfire Insurance Fund will terminate when the administrator determines that the fund has been exhausted. Management reassesses the period of coverage of the fund at least annually in January each year and adjustments are applied on a prospective basis. In January 2023, management estimated that the Wildfire Insurance Fund will provide insurance coverage for a period of 15 years from the date SCE committed to participate in the Wildfire Insurance Fund. The determination of the correct period in which to record an expense in relation to contributions to the Wildfire Insurance Fund depends, among other factors, on management's assessment of: the future occurrence and magnitude of wildfires; the involvement of SCE, or other electrical corporations which could access the Wildfire Insurance Fund, in the ignition of those fires; the probable future outcomes of CPUC cost recovery proceedings for wildfire claims, which may require reimbursement of the fund by electrical corporations; and the use of the contributions by the administrator of the Wildfire Insurance Fund. Further information regarding these factors may become available due to the actions of the fund administrator, or other entities, which could require management to reassess the period of coverage. In estimating the period of coverage, Edison International and SCE used Monte Carlo simulations based on nine years (2014 – 2022) of historical data from wildfires caused by electrical utility equipment to estimate expected loss. The details of the operation of the Wildfire Insurance Fund and estimates related to claims by SCE, PG&E and SDG&E against the fund have been applied to the expected loss simulations to estimate the period of coverage of the fund. The most sensitive inputs to the estimated period of coverage are the expected frequency of wildfire events caused by investor-owned utility electrical equipment and the estimated costs associated with those forecasted events. These inputs are most affected by the historical data used in estimating expected losses. Using a 16-year period (2007 – 2022) of historical data would further increase the period of coverage.

Based on information available in January of 2024 regarding catastrophic wildfires during 2023, SCE reassessed its estimate of the life of the Wildfire Insurance Fund. After incorporating 2023 expected losses into the historical data for the Monte Carlo simulations, SCE determined that effective in the first quarter of 2024, the life of the Wildfire Insurance Fund is expected to increase to 20 years from the date SCE committed to participate in the Wildfire Insurance Fund.

Effect if Different Assumptions Used. Changes in the estimated life of the insurance fund could have a material impact on the expense recognition.

NEW ACCOUNTING GUIDANCE

New accounting guidance is discussed in "Notes to Consolidated Financial Statements—Note 1. Summary of Significant Accounting Policies—New Accounting Guidance."